ASBCA 60476
Board: ASBCA
Agency: Air Force
Appellant: Thorington Electrical and Construction Company
Date: 2017-02-16
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Thorington Electrical and Construction Company ) ASBCA No. 604 76
)
Under Contract No. FA3300-05-C-0015 )
APPEARANCES FOR THE APPELLANT: Deitra Crawley, Esq.
Natalie Mark, Esq.
Taylor English Duma LLP
Atlanta, GA
APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq.
Air Force Deputy Chief Trial Attorney
Lawrence M. Anderson, Esq.
Trial Attorney
OPINION BY ADMINSTRATIVE JUDGE PROUTY
ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT
Before us is the government's motion for summary judgment, which argues that
the claim appealed here by appellant, Thorington Electrical and Construction Company 1
(Thorington), is time-barred under the Contract Disputes Act of 1978 (CDA), 41 U.S.C.
§§ 7101-7109. Thorington opposes the government's motion, arguing that its claim was
timely because it is an amendment of an earlier claim of which the government was on
notice. For the reasons stated herein, we conclude that the claim is time-barred under the
CDA and enter judgment in favor of the government.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. On 30 September 2005, the United States Air Force (government) awarded
Contract No. FA3300-05-C-0015 (the contract) to Thorington for the construction of a
new entry control facility at the Bell Street Gate at Maxwell Air Force Base, Alabama
(R4, tab 1).
2. The construction of the facility was substantially completed by 11 August 2008,
when the government determined that it was "fully operational" (compl. ~~ 32, 34).
1
Contract was awarded to "Thorington Electrical/Construction Company" but the claim
and correspondence herein replaces the backslash (/) with "and."
3. On 28 April 2009, Thorington submitted a letter to the contracting officer (CO)
seeking $764,813 in compensation from the government (R4, tab 48). The letter was
labeled as a "claim" and was certified by Thorington's general manager and owner,
Mr. Kelvin R. Thorington (id.). The letter provided that, "[t]he items that [Thorington]
is making a claim [upon] are associated with work that was performed but was never paid
and material cost for items increased since submitting the original cost estimate in 2005"
(id. at 1). Thorington also stated, in relevant part:
In Addition, the claim does not include cost that TECC
[Thorington] has acquired or projects that TECC could have
obtained over the last six months. The delay in paying the
modifications has caused TECC to lose several projects over
the past year. As stated in several letters to the CO, the
impact of nonpayment towards these modifications has
caused delays in TECC paying our sub-contractors in a timely
manner. This delay in payment has also caused the sub-
contractors and venders [sic] to file claims against the surety
company. If all modifications had been paid in a timely
manner, TECC could have paid the sub-contractors and
venders [sic] which would have eliminated any intervention
by the surety company. Once the surety company pays any
claims it is detrimental to your company's future ability to
bond. The extended performance time occupied our bonding
because the government delayed the project for
approximately 1 Yi years and continues to occupy our
bonding capabilities until the modifications are settled. These
additional claims will be submitted through the legal system
at a later date but with-in the next few months.
(Id. at 6)
4. By letter dated 14 August 2009, the CO issued a final decision
partially granting and partially denying Thorington's claim dated 28 April
2009 (R4, tab 49).
5. Thorington appealed the CO's decision to this Board, and the appeal was
docketed on 17 November 2009 as ASBCA Nos. 56987, 56988, 56989, 56990, 56991,
56992, 56993, 56994, 56995, 56996, 56998, 56999 and 57000. These appeals were
all resolved when Thorington signed an agreement, dated 18 August 2015, which
resolved all of its claims dated 28 April 2009 (gov't mot., attach. 1).