ASBCA 61493
Board: ASBCA
Agency: United States Army Corps of Engineers
Appellant: Watts Constructors, LLC
Date: 2020-03-19
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Watts Constructors, LLC ) ASBCA No. 61493
)
Under Contract No. W91238-14-C-0040 )
APPEARANCES FOR THE APPELLANT: Jason R. Thornton, Esq.
Jeffrey B. Baird, Esq.
Daniel P. Scholz, Esq.
Finch, Thornton & Baird, LLP
San Diego, CA
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
A.L. Faustino, Esq.
Robert W. Scharf, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Sacramento
OPINION BY ADMINISTRATIVE JUDGE PROUTY
Before us is a dispute about whether the terms of the above-captioned contract (the
contract) for the construction of several buildings required appellant, Watts Constructors,
LLCâs (Watts), electrical subcontractor to run electrical power lines in the buildings
through rigid conduit as opposed to using more economical integrated metal clad (MC)
cable. 1 Wattsâs electrical subcontractor, Helix Electric, Inc. (Helix), saw what it wished
to see when it reviewed the contractâs plans and specifications and used MC cable
extensively in the construction. This was visible to quality assurance inspectors from the
contracting agency, the United States Army Corps of Engineers (the Corps), but not
objected to by the Corps until relatively late in the game. As will be discussed at length
below, standard contract interpretation supports the Corpsâ reading of its contract,
requiring the exclusive use of conduit, not MC. Moreover, though it would have been far
better for the quality assurance inspectors from the Corps to have recognized and halted
Helixâs divergence from the requirements of the contract, their inaction did not change
the meaning of the contract and was insufficient to support a finding of waiver of
contractual compliance by the government.
1
The reader has likely seen MC cable in their experience: itâs an electrical power
conductor surrounded by flexible grey metal as a single assembly (tr. 20; see also
R4, tab 61 (photo) and tr. 165-66 (describing photo)). It comes in spools (tr. 91).
FINDINGS OF FACT
I. Contract And Subcontract Awards
In the mid-2000s, the United States Army decided to build a facility for satellite
communications on Camp Roberts, California near the town of Paso Robles (tr. 131 2
(inception of project in 2006)). The contract to accomplish this goal encompassed the
construction of four buildings: a satellite communications operations center (by far, the
largest of the buildings); a command/administrative support center; a repair and utilities
building; and a covered storage shed (R4, tab 2 at 1). This contract, in the amount
of $38,914,500, was awarded to Watts on September 3, 2014 (R4, tab 2 at 2). Shortly
thereafter, Watts executed a subcontract agreement with Helix to perform all of the
electrical work on the project (R4, tab 52 at 14-35; tr. 17-19).
The contract contained the standard Changes clause, to be found in Federal
Acquisition Regulation (FAR) Part 52.243-4 providing authority of the contracting
officer to change the terms of the contract (R4, tab 2 at 15-16).
II. The Contractual Requirements Relating To Wiring
The Corps has an institutional preference for utilizing rigid conduit to run electric
power cable in buildings that it has constructed (tr. 150, 175). This is because the Corps
believes that conduit-installed power lines will last longer (tr. 175-76). Helix personnel
were well aware of this general desire (tr. 79), but held their own preference for power
cabling, which was the use of flexible MC (tr. 22, 35, 81). As we will explain in
Section III, below, although MC shares some of its characteristics, MC is not conduit.
Despite their concerns that the Corps would not permit the use of MC, Helix
personnel involved in planning the construction found portions of the contractâs
specifications that, they believed, permitted the use of MC cable throughout and which
we note below (tr.