ASBCA 63898
Board: ASBCA
Agency: U.S. Army Corps of Engineers
Appellant: Jabez-Absher Small Business Joint Venture
Date: 2025-10-02
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Jabez-Absher Small Business Joint ) ASBCA No. 63898
Venture )
)
Under Contract No. W912DW-22-C-0011 )
APPEARANCES FOR THE APPELLANT: Mr. Stephen Montalvo
Project Executive
Kainui M. Smith, Esq.
Counsel
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Benjamin T. Townsend, Esq.
Anna Astrakhan, Esq.
Eric M. Smith, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Seattle
OPINION BY ADMINISTRATIVE JUDGE TAYLOR
PURSUANT TO BOARD RULE 11
Jabez-Absher Small Business Joint Venture (Jabez-Absher or appellant) seeks
an increase in the contract price of $100,865.76 resulting from its decision to change
the production facility for certain electrical equipment. Jabez-Absher contends it was
required to change the production facility since the lead time for the equipment from
the original production facility had increased from 50 to 80 weeks negatively
impacting the construction schedule. Jabez-Absher further contends that it provided
the U.S. Army Corps of Engineers (USACE or government) with notice of this change
and the government acknowledged the change.
Jurisdiction is proper pursuant to the Contract Disputes Act of 1978 (CDA),
41 U.S.C. §§ 7101–7109. The parties have elected for the Board to decide this appeal
pursuant to the Board’s Rule 11 procedures. Board Rule 11 permits the parties to
waive a hearing and submit the matter for decision on the written record. Pursuant to
Rule 11, the Board decides the weight to be given the evidence and may make findings
of fact on disputed facts. Board Rule 11(d). For the reasons stated below, the appeal
is denied.
FINDINGS OF FACT
I. The Contract
On August 23, 2022, the USACE awarded Jabez-Absher a firm-fixed price
contract in the amount of $29,004,500 to repair a military barracks on Joint Base
Lewis-McChord (R4, tab 3). The contract had a completion date of 720 calendar days
from the date of the notice to proceed (id. at 33). 1 The government issued the notice to
proceed on September 7, 2022, with an effective date of October 3, 2022, establishing
a contract completion date of September 22, 2024 (R4, tab 9). The contract stated the
contractor shall supply all supervision, labor, equipment and materials necessary to
perform the required work (R4, tab 3 at 33).
The contract also specifically notified Jabez-Absher that only a warranted
contracting officer had the authority to change the contract’s terms and conditions, and
the contractor should not proceed with any attempted changes made by someone other
than a warranted contracting officer without first notifying the contracting officer (R4,
tab 3 at 37). Proceeding with such unauthorized work would be at the contractor’s
own risk (id.).
The contract incorporated by reference Federal Acquisition Regulation (FAR)
52.243-4, CHANGES (JUN 2007) which provides, in relevant part:
(b) Any other written or oral order . . . from the
Contracting Officer that causes a change shall be treated as
a change order under this clause; provided, that the
Contractor gives the Contracting Officer written notice
stating (1) the date, circumstances, and source of the order
and (2) that the Contractor regards the order as a change
order.
(c) Except as provided in this clause, no order, statement,
or conduct of the Contracting Officer shall be treated as a
change under this clause or entitle the Contractor to an
equitable adjustment.
(Id. at 45) (emphasis added)
1
The government’s Rule 4 file is Bates numbered with a five-digit number. We omit
the leading zeros in our citations to the government’s Rule 4 file.
2
II. The Electrical Subcontract
Jabez-Absher issued a subcontract to Danard Electric, Inc. (Danard) to perform
the electrical work on the contract (Appellant’s Statement of Facts (ASOF) ¶ 3).