CBCA 4750-C(3552)
Board: CBCA
Appellant: Impact Associates, Inc.
Date: 2016-08-31
GRANTED IN PART: August 31, 2016
CBCA 4750-C(3552)
IMPACT ASSOCIATES, INC.,
Applicant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Andrew K. Wible and William F. Savarino of Cohen Mohr LLP, Washington, DC,
counsel for Applicant.
Michael J. Noble, Office of General Counsel, General Services Administration,
Washington, DC, counsel for Respondent.
Before Board Judges VERGILIO, SHERIDAN,1 and ZISCHKAU.
VERGILIO, Board Judge.
Impact Associates, Inc. (applicant) prevailed in the appeal, Impact Associates, Inc. v.
General Services Administration, CBCA 3552, 15-1 BCA ¶ 35,910, underlying this timely
filed application for recovery pursuant to the Equal Access to Justice Act (EAJA), 5 U.S.C.
§ 504 (2012). Maintaining that it satisfies the requirements in terms of net worth and number
of employees and that the position of the Government was not substantially justified, the
1
Because of the retirement of one judge, the panel has changed from the
underlying appeal.
CBCA 4750-C(3552) 2
applicant seeks to recover $27,025.20 in attorney fees and costs. The General Services
Administration (GSA) recognizes that the applicant was a prevailing party before this Board,
does not challenge the net worth or size assertions, and does not allege that its position before
the Board was substantially justified. However, GSA seeks to subtract from the relief sought
the amount expended in initially pursuing the appeal at the Armed Services Board of
Contract Appeals (ASBCA) (which dismissed the matter for lack of jurisdiction) and reduce
the remaining amount by ten percent because the applicant did not recover the full amount
of its claim (it dropped an item of recovery, reducing the amount sought by $40,000).
The Board concludes that the applicant shall recover the full amount sought only for
the period after receipt of the GSA contracting officerâs decision. The activities prior to
receiving the denial of the claim underlying this appeal, while reasonable and necessary steps
for the applicant to obtain relief, are not compensable. While the applicant dropped an item
of relief from its claim, the record does not support the conclusion that the award of relief
here should be reduced for that reason. The applicant recovers $5612.50.
Findings of Fact
By way of background, the applicant held a GSA schedule contract. The applicant
entered into a no-cost task order contract with the United States Army Corps of Engineers
(Corps) thereunder. The applicant provided technical assistance support to plan and conduct
forums. Under the task order, the agreement provided that the applicant could not claim
against the Government for any costs or other damages that the applicant might incur by
Government-required changes, a reduction in participation, or withdrawal. Under the task
order, the applicant retained mandatory registration and exhibition fees and sponsorship
monies; these were the applicantâs sources of income under the task order. During an option
year, the Corps required the applicant to eliminate all forms of corporate sponsorship,
otherwise altered the applicantâs ability to recover its costs, and required the applicant to
expend monies it would not have otherwise. Seeking to recover $215,183.79, in August
2010, the applicant submitted a certified claim to a Corps contracting officer, who denied the
claim. The applicant appealed to the ASBCA on May 11, 2011. After twice concluding that
it had jurisdiction, the ASBCA reconsidered the question in light of an opinion by the Federal
Circuit issued on February 23, 2013, Sharp Electronics Corp. v. McHugh, 707 F.3d 1367,
1374-75 (Fed. Cir. 2013) (the court held that the ordering agency contracting officer has no
authority to decide a claim requiring interpretation of the schedule contract), and on April 19,
2013, dismissed the appeal for lack of jurisdiction, concluding that the issue involved
interpretation of the schedule contract. Impact Associates, Inc., ASBCA 57617, 13 BCA
¶ 35,289. Thereafter, the applicant referred the claim to a GSA contracting officer, who, in
August 2013, affirmed the claim, seemingly in terms of entitlement only, because payment
did not occur. Seeking to reduce the contracting officerâs decision to a final judgment, in
CBCA 4750-C(3552) 3
September 2013 the applicant filed at this Board the appeal underlying this case.