CBCA 2326
Board: CBCA
Agency: Environmental Protection Agency
Appellant: ASW Associates, Inc.
Date: 2018-02-23
Outcome: denied
DENIED: February 23, 2018
CBCA 2326
ASW ASSOCIATES, INC.,
Appellant,
v.
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
Robert B. Creager of Anderson, Creager & Wittstruck, P.C. LLO, Lincoln, NE,
counsel for Appellant.
Sara E. McGraw and Kenneth R. Pakula, Office of General Counsel, Environmental
Protection Agency, Washington, DC, counsel for Respondent.
Before Board Judges VERGILIO, GOODMAN, and SULLIVAN.
VERGILIO, Board Judge.
ASW Associates, Inc. (contractor or ASW) remediated lead-contaminated soil at a
superfund site under a contract with the Environmental Protection Agency (agency or EPA).
The contractor was paid for labor hours and equipment usage at the rates in the underlying
contract, but the number of properties remediated, as well as labor hours and equipment
usage were below the estimates in the contract. The agency did not exercise option year two.
In its claim, and as pursued in its complaint, the contractor contends that the agency both
improperly interfered with or hindered the contractorâs ability to direct and manage the work,
and misrepresented the scope and quantity of work to be performed. The contractor seeks
to recover a total of $1,801,858.53, broken down as follows with the contractorâs
terminology (not Board calculations):
CBCA 2326 2
base year: personnel, equipment, delta for unilateral g&a of 15% $ 755,153.80
option 1: personnel, equipment, delta for unilateral g&a of 15% $ 604,420.73
option 2: equipment only $ 442,284.00
The Board previously dismissed one aspect of the underlying appeal (the contractor
alleged that the agency interfered with or hindered the contractorâs performance, but failed
to provide any evidence to support its allegation), and then determined that the agreement is
not enforceable as either an indefinite delivery/indefinite quantity (ID/IQ) or a requirements-
type contract. ASW Associates v. Environmental Protection Agency, CBCA 2326, 16-1 BCA
¶ 36,453, 17-1 BCA ¶ 36,699. In the latter decision, the Board directed the contractor to
identify what, if any, additional payment it seeks, its bases for asserting entitlement, and its
method of calculation. The Board also issued directives further specifying what the
contractor had to do (âthe contractor must flesh out any aspect of its claim that it asserts
survives and that it seeks to pursue,â Board Order (May 22, 2017); âthe agency and Board
have sought the information (legal theory and costs sought, with support) since well before
counsel represented the contractor,â Board Order (June 13, 2017)).
Despite the Boardâs direction, the contractor has not identified in the record or stated
in its submissions in response how it arrived at its calculations or provided any support for
the basic figures, and has failed to tie the amounts sought to each theory of relief it pursues.
The contractor has stated that it has no additional claim for payment given the Boardâs
determination that the contractor was limited to payment on a time and materials basis, while
otherwise preserving its appeal rights. It amended that response to state that it has no
additional claim for payment based upon the equitable principles in a case referenced by the
Board, but that its claim is for work that it was not allowed to perform or work that was
provided by other contractors. The contractor continues to seek relief under theories of
negligence and cardinal change. The contractor has provided no details or explanation in
support of the dollars sought. At this stage in the proceedings the contractor seeks a sum
certain that is allocated between the base year, option year, and un-exercised option year.
The agency moved for summary relief on the aspects of the claim that remain in this
appeal (assertions of agency negligence and cardinal change), accurately noting that the
contractor failed to provide factual support for its monetary claim in response to previous
Board orders and directives. The contractor provided no substantive response to the motion.
It asserts that it contracted to remediate all of the work identified in the contract and priced
the cost of providing the labor and equipment based upon the total amount of work identified.
The contractor provides no proof of its pricing with its response.