CBCA 7385-R
Board: CBCA
Agency: Department of Homeland Security
Appellant: True Excellence Group, LLC
Date: 2023-05-04
Outcome: denied
MOTION FOR RECONSIDERATION DENIED: May 4, 2023
CBCA 7385-R
TRUE EXCELLENCE GROUP, LLC,
Appellant,
v.
DEPARTMENT OF HOMELAND SECURITY,
Respondent.
John M. Manfredonia of Manfredonia Law Offices, LLC, Cresskill, NJ, counsel for
Appellant.
Ekta Patel and Bruce M. James, Office of Chief Counsel, Federal Emergency
Management Agency, Department of Homeland Security, Washington, DC, counsel for
Respondent.
Before Board Judges GOODMAN, SHERIDAN, and ZISCHKAU.
SHERIDAN, Board Judge.
Appellant, True Excellence Group, LLC (TEG), seeks reconsideration of our decision
dated March 7, 2023. TEG raises a single argument on reconsiderationâthat the Board
applied the ten-tent minimum to the base period only and did not apply the minimum to each
of the option periods exercised under the indefinite-delivery, indefinite-quantity (IDIQ)
contract. We deny TEGâs motion.
CBCA 7385-R 2
Background
As discussed in our previous decision in this appeal, True Excellence Group, LLC v.
Department of Homeland Security, CBCA 7385, 23-1 BCA ¶ 38,299, FEMA awarded TEG
an IDIQ contract on January 27, 2020, to provide Mobile Disaster Recovery Centers
(MDRCs) for delivery of FEMAâs disaster relief services to survivors of an earthquake in
Puerto Rico. The initial period of performance under the contract was six months, with three
one-month option periods (the IDIQ options).
On April 22, 2022, TEG filed a notice of appeal with the Board. TEG alleged in its
appeal the following: (1) that FEMA had failed to meet the guaranteed minimum under the
contract, (2) that FEMA breached the contract by not paying for costs associated with the
task order options, (3) that FEMA failed to disclose superior knowledge, (4) that FEMA
breached the implied duty of good faith and fair dealing, and (5) that FEMA violated the
Small Business Act, 15 U.S.C. § 632 (2018), and the Prompt Payment Act, 31 U.S.C. § 3903.
FEMA moved to dismiss the appeal on two primary grounds: (1) that the Board
lacked jurisdiction over TEGâs claim regarding the guaranteed minimum and (2) that TEG
failed to state a claim for breach of contract upon which relief may be granted with regard
to TEGâs remaining claims.
In its decision, the Board found that (1) we lacked jurisdiction over TEGâs mandatory
minimum claim, (2) the contract was a proper IDIQ contract where the mandatory minimum
was contained in the statement of work (SOW), (3) FEMAâs exercise of the IDIQ options did
not effectively cause the exercise of the task order options, and (4) appellant had failed to
state a claim for breach of contract upon which relief may be granted.
On March 28, 2023, appellant timely filed a motion for reconsideration consistent
with Board Rule 26(c) (48 CFR 6101.26(c) (2021)).
Discussion
âA motion for reconsideration must be based on the acquisition of newly discovered
evidence or the showing of legal error.â Yates-Desbuild Joint Venture v. Department of
State, CBCA 3350-R, et al., 18-1 BCA ¶ 36,959, at 180,084 (2017) (quoting Sims Paving
Corp., DOT BCA 1822, 91-2 BCA ¶ 23,733, at 118,868).
Appellantâs claim submitted to the contracting officer sought payment of the firm-
fixed, not-to-exceed values of nine task orders on the basis that an exercise of an option
under the IDIQ contract extended each of the task orders issued during the base period. In
our decision, we found this to be contrary to the law regarding the exercise of option periods.
CBCA 7385-R 3
Now, on reconsideration, appellantâs claim of error is that the Board applied the ten-tent
minimum to the base period only and did not apply that minimum to each of the option
periods exercised under the IDIQ contract.
Appellant misunderstands our original decision. While we found in our original
decision that the SOW created the mandatory minimum required for a proper IDIQ contract,
we did not (and do not now) decide whether or not the contract created separate, enforceable
minimums for each of the option periods.1
Ultimately, we lack jurisdiction over this claim by appellant. We have already
dismissed appellantâs claim regarding whether FEMA met the mandatory minimum under
the base contract for a failure to present it to the contracting officer. True Excellence, 23-1
BCA at 185,949. Here, appellantâs claim that FEMA failed to meet required minimums
under the options comes to the same result.