CBCA 8002
Board: CBCA
Agency: Department of Homeland Security
Appellant: MLU Services, Inc.
Date: 2024-09-09
Outcome: dismissed
DISMISSED IN PART FOR LACK OF JURISDICTION; DENIED IN PART:
September 9, 2024
CBCA 8002
MLU SERVICES, INC.,
Appellant,
v.
DEPARTMENT OF HOMELAND SECURITY,
Respondent.
Allison G. Geewax of Smith Currie Oles LLP, Tysons, VA; and Lochlin B. Samples
of Smith Currie Oles LLP, Atlanta, GA, counsel for Appellant.
Andrew Michael Thabo Hickey, Office of Chief Counsel, Federal Emergency
Management Agency, Department of Homeland Security, Washington, DC, counsel for
Respondent.
Before Board Judges LESTER, RUSSELL, and SULLIVAN.
LESTER, Board Judge.
Appellant, MLU Services, Inc. (MLU), has appealed a decision of a contracting
officer for the Federal Emergency Management Agency (FEMA) that both denies a monetary
claim that MLU submitted and asserts a government claim. The FEMA contracting officer
denied MLUâs claim challenging FEMAâs non-payment of five invoices (only three of which
MLU is pursuing in this appeal) that MLU alleges, but FEMA denies, MLU had previously
submitted for payment. The FEMA contracting officer also asserted a government claim
under the anti-fraud provision of the Contract Disputes Act (CDA), 41 U.S.C. § 7103(c)(2)
(2018) (section 7103(c)(2)), seeking penalties on the unsupported part (allegedly the entirety)
CBCA 8002 2
of MLUâs monetary claim, plus reimbursement of FEMAâs costs incurred in reviewing
MLUâs claim.
Addressing MLUâs monetary claim, FEMA filed a motion seeking summary judgment
in its favor because, before MLU submitted its claim, MLU had not submitted its invoices
for payment in the manner that its task orders required, meaning that FEMAâs obligation to
process and pay those invoices had never accrued. Because MLU does not dispute that it did
not formally submit the invoices to FEMA for payment in conformance with the contractâs
required process and because MLU provides no evidentiary support for its allegation that
FEMA informally agreed to change the contractually required method for the formal
submission of invoices, FEMA is entitled to summary judgment on MLUâs claim challenging
FEMAâs non-payment. MLUâs more recent submission of the invoices to FEMA in
accordance with the contract requirements, which occurred after MLU submitted its certified
claim, is not properly before us, and our decision here does not preclude MLU, outside of the
context of this appeal, from pursuing payment on invoices that it properly submitted after
submitting its certified claim.
Addressing FEMAâs monetary claim, which seeks penalties under section 7103(c)(2)
arising out of MLUâs alleged fraud, MLU requests that we âstrikeâ that claim because the
contracting officer did not possess authority to have issued a final decision asserting the
government claim. MLU is correct that contracting officers lack authority to issue CDA
decisions seeking recovery under section 7103(c)(2), meaning that the FEMA contracting
officerâs decision purporting to do so is void and unenforceable. We reject FEMAâs
argument that, because the Board lacks authority to consider fraud, the contracting officerâs
decision imposing penalties under section 7103(c)(2) is essentially unappealable and
untouchable. Instead, we find that, because the contracting officerâs decision asserting an
affirmative monetary claim under section 7103(c)(2) is void, there is no valid decision
asserting the purported government claim upon which to base jurisdiction of MLUâs appeal
of that claim.1
Background
I. The Terms of Task Orders 18, 43, and 55
On April 3, 2018, FEMA awarded contract 70FB8018D00000013, known as the
âLogistics Housing Operations Unit Installation Maintenance and Deactivationâ
1
We similarly lack jurisdiction to entertain additional monetary demands that
FEMA included in an addendum to its answer because the contracting officer never asserted
entitlement to those costs in the contracting officerâs final decision on appeal.
CBCA 8002 3
(LOGHOUSE) contract, to MLU. Appeal File, Exhibit 2 at 582, 643.2 The LOGHOUSE
contract was an indefinite-delivery/indefinite-quantity contract with a cost ceiling of $730
million that was intended to support FEMAâs manufactured housing unit mission. Id.