CBCA 7771
Board: CBCA
Agency: Department of the Interior
Appellant: Comp Environmental, Inc.
Date: 2025-05-23
Outcome: denied
MOTION TO DISMISS DENIED: May 23, 2025
CBCA 7771, 7830
COMP ENVIRONMENTAL, INC.,
Appellant,
v.
DEPARTMENT OF THE INTERIOR,
Respondent.
Caroline Wang, President of Comp Environmental, Inc., Winter Haven, FL,
appearing for Appellant.
Brian A. Quint, Office of the Solicitor, Department of the Interior, Washington, DC,
counsel for Respondent.
Before Board Judges BEARDSLEY (Chair), SHERIDAN, and ZISCHKAU.
ZISCHKAU, Board Judge.
Respondent, the Department of the Interior, United States Fish and Wildlife Services
(FWS), has moved to dismiss Comp Environmental, Inc.’s (CEI) appeals for failure to state
a claim upon which relief may be granted. FWS argues that CEI is not entitled as a matter
of law to increased costs that CEI claims were incurred due to added backfill required by
government permitting requirements, permitting delays, and material price escalation. CEI,
however, has presented factual allegations that plausibly suggest entitlement to relief.
Accordingly, we deny FWS’s motion.
CBCA 7771, 7830 2
Background
On September 5, 2019, FWS issued a statement of work (SOW) for design-build
services to rehabilitate two existing parking areas and add a new graveled parking area at the
Arthur R. Marshall Loxahatchee National Wildlife Refuge in Boynton Beach, Florida.
Exhibit 1 at 1, 19-20.1 On May 20, 2020, FWS issued amendment 1 to the SOW which
(1) increased the length of Lee Road to be rehabilitated; (2) added restriping of existing
parking lots; and, relevant to the dispute here, (3) increased from 24,000 square feet (sq. ft.)
to 54,222 sq. ft. the area of the Hillsboro parking lot that need to be rehabilitated. Exhibits 3,
A010 at 69. On June 25, 2020, CEI submitted its bid schedule to FWS. Exhibit 4. CEI’s
bid schedule included, “Design-Build Rehabilitate Hillsboro Parking Area” for “up to
8 [inches] DOT Certified Limerock base. Limited subbase repairs. Regrading limerock
base.” Id. In July 2020, FWS awarded the contract to CEI, accepting CEI’s bid schedule for
a total price of $389,630. The design and construction services for rehabilitating the
Hillsboro parking area were priced at $164,630. Exhibit 5.
SOW section 6, entitled “Specific Project Requirements,” contains a subsection c.,
entitled “Permit Application Assistance.” Exhibit 1 at 19, 21. This subsection required CEI
to “[a]ssist the Manager of Arthur R. Marshall Loxahatchee National Wildlife Refuge in the
permit application process for state and local permits, Corps of Engineers approvals and
other required permits by providing permittable drawings, engineering data and other
technical information required by the permitting authority.” Id. at 21.
On September 23, 2020, FWS and CEI entered into bilateral modification P00001
(mod 1) to include construction services costs for rehabilitating the boat access ramp area.
Exhibit 6. Attached to and made a part of mod 1 was CEI’s revised bid schedule dated
September 9, 2020, which included the same note as in the original bid schedule indicating
that the Hillsboro parking area work item is for “up to 8 [inches] DOT Certified Limerock
base. Limited subbase repairs. Regrading limerock base.” Id. at 3.
In a letter dated March 16, 2021, FWS first applied for a permit to the South Florida
Water Management District (SFWMD). Exhibit A001. At the end of the letter, FWS
appointed CEI as the “agent to assist with this permit application.” Id. at 2. On April 7,
2021, SFWMD inspected the project site. Exhibit A010 at 147. On April 14, 2021, SFWMD
stated, “It appears that the L-39 levee does not meet the minimum design cross section
requirements at this location.” Exhibit A010 at 152. On May 10, 2021, modification P00002
(mod 2), valued at $64,648.20, was created for “construct[ing] Hillsboro drain pipe & curb”
and “Lee Road centerline paint striping.” Exhibit 7 at 2, 4. Mod 2 states that “[a]ll other
1
All exhibits are found in the appeal file, unless otherwise noted.
CBCA 7771, 7830 3
terms and conditions remain unchanged” and thus left unchanged CEI’s quantity limitation
of “up to 8 [inches] subbase” which was incorporated into the contract. CEI was onsite
between contract award and mod 2, but construction had not commenced because of
permitting delays.
On May 16 and July 15, 2021, SFWMD exchanged internal emails about the levee
needing to “be brought to minimum with select fill then the gravel be added on top of that.”
Exhibit A010 at 127-30, 136-37.