CBCA 4545
Board: CBCA
Agency: General Services Administration
Appellant: Grunley Construction Co., Inc.
Date: 2016-11-29
Outcome: denied
MOTIONS FOR CLARIFICATION AND RECONSIDERATION DENIED:
November 29, 2016
CBCA 4545
GRUNLEY CONSTRUCTION CO., INC.,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Lawrence M. Prosen and Daniel P. Broderick of Kilpatrick Townsend & Stockton
LLP, Washington, DC, counsel for Appellant.
Jay N. Bernstein, Office of General Counsel, General Services Administration,
Washington, DC, counsel for Respondent.
Before Board Judges DANIELS (Chairman), DRUMMOND, and RUSSELL.
DANIELS, Board Judge.
On October 27, 2016, the Board issued a decision granting in part and denying in part
cross-motions filed by the parties, Grunley Construction Co., Inc. (Grunley) and the General
Services Administration (GSA), for partial summary relief in two appeals, CBCA 4539 and
CBCA 4545. Grunley Construction Co. v. General Services Administration, CBCA 4539,
et al., 16-1 BCA ¶ 36,536. Both parties have asked us to reconsider portions of the decision,
and Grunley has also asked us to clarify one part of the decision.
CBCA 4545 2
We note first the aspects of the decision to which the clarification and reconsideration
motions are not directed. Neither party takes exception to our ruling in CBCA 4539,
regarding the wage determination claim, or to our ruling in CBCA 4545 as to markups on the
additional asbestos claim. We consequently do not address those parts of the decision here.
The clarification and reconsideration motions concern the principal issues in CBCA
4545 â what was indicated on the contract drawings and whether Grunley gave GSA
sufficient notice of what the contractor considers differing site conditions, so as to avoid
prejudicing the agency in responding to the claim.
As to the first of these issues, the parties had different positions regarding the portions
of the contract the contractor should have considered as showing the asbestos to be abated.
Grunley maintained that it properly relied only on the hazardous materials, or hazmat,
drawings, as showing that asbestos, while GSA contended that the contractâs mechanical,
electrical, and plumbing, or MEP, drawings â and an appendix to section 02085 of the
specifications â were relevant as well. We agreed with GSAâs position. 16-1 BCA at
177,990. Grunley moves for reconsideration of this ruling. In doing so, however, it merely
reargues the points it made earlier. âArguments already made and reinterpretations of old
evidence are not sufficient grounds for granting reconsideration.â Rule 26(a) (48 CFR
6101.26(a) (2015)). This motion is denied.
Grunleyâs motion for clarification asks whether we meant to say that if horizontal
piping was shown on the hazmat drawings without asbestos containing material (ACM) and
also depicted on the MEP drawings as requiring demolition, the contractor should have
anticipated ACM on that piping. The motion for clarification also asks whether, if neither
the hazmat drawings nor the MEP drawings depicted a horizontal pipe, we meant to say that
the contractor should have anticipated that the piping it found was wrapped with ACM.
These questions go to matters beyond what the parties presented for a ruling in their
cross-motions for summary relief. The questions may be hypothetical, as well; Grunley
asserts that â[n]one of the pipe for which Grunley is claiming entitlement for additional
asbestos abatement work was shown on the MEP Drawings or the Hazmat Drawings,â and
GSA responds that it âvigorously disputes this contention.â An analysis of the matters raised
in the motion for clarification will best be provided after development of the record. The
motion is denied. We do note in this regard, though, that GSA has effectively conceded that
it erred by saying, in its Statement of Undisputed Fact number 14, that â[t]he G400 series of
hazmat drawings . . . do not depict any of the horizontal piping.â We incorporated this
statement into our decision. The agency now tells us, in response to the contractorâs motion,
CBCA 4545 3
that hazmat drawing G402B, which shows the buildingâs ground floor, depicts some
horizontal piping.1
As to the second principal issue in CBCA 4545, whether Grunley gave sufficient
notice, we reported that the contractor sent the agency two separate requests for information
(RFIs) regarding asbestos it found but had not expected â RFI 175, on April 30, 2006, and
RFI 408, in early January 2007.