ASBCA 58082
Board: ASBCA
Agency: Navy
Appellant: Alderman Building Company, Inc.
Date: 2020-05-21
Outcome: sustained in part
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Alderman Building Company, Inc. ) ASBCA No. 58082
)
Under Contract No. N40085-09-D-5321 )
APPEARANCE FOR THE APPELLANT: Marilyn H. David, Esq.
DâIberville, MS
APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq.
Navy Chief Trial Attorney
Genifer M. Tarkowski, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE YOUNGER
In this sponsored appeal regarding a contract for the renovation and interior repair
of a building, Alderman Building Co., Inc. (Alderman), seeks unabsorbed home office
overhead on behalf of its electrical subcontractor relating to performance delays. The
issues are heavily fact-intensive, and we have previously denied motions for summary
judgment filed by both parties. After disposition of their summary judgment motions, the
parties elected to submit the appeal on the record pursuant to our Rule 11 and
supplemented the record with additional documents. Both entitlement and quantum are
before us for decision. We sustain the appeal in part.
FINDINGS OF FACTS
A. Contract and Subcontract
1. By date of March 27, 2009, the Navy awarded a Task Order for supplies or
services under Contract No. N40085-09-D-5321 to Alderman for renovations of the
interior, repairs to building systems, and incidental related work, on building M403
at Marine Corps Base Camp Lejeune, North Carolina (R4, tab 1 at 1-7). The
Task Order provided that â[t]he entire work . . . shall be completed by 3/22/2010â
(id. at 7).
2. The contract contained various standard clauses, including Federal Acquisition
Regulation (FAR) 52.233-1, DISPUTES (JUL 2002); FAR 52.242-14, SUSPENSION OF
WORK (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 5.6 at 958).
3. By date of April 8, 2009, Alderman entered into a subcontract with
Big Johnâs Electric Co., Inc. (Big Johnâs), for labor, equipment, materials, and
supplies for specified portions of the interior repairs to the building (R4,
tab 5.12 at 995). Big Johnâs was an electrical subcontractor that performed
approximately 90 percent of its work on Federal projects (ex. A-1, tab 40 ¶¶ 2-27).
The subcontract provided that âtime is of the essence,â and that Big Johnâs was to
âbegin work within 7 days after notificationâ by Alderman (R4, tab 5.12 at 996).
B. Delays
4. Approximately two months after award, by email dated May 27, 2009, the
Navy directed Alderman to â[c]ontinue to get all of your submittals approved and
ready to start construction and we will move the [contract completion date]â
accordingly when we have a nailed down work start dateâ (R4, tab 5.13). We find
that the Navy expected the work to be initiated with full force by all parties.
5. While the solicitation provided that the contract start date would be
10 days after award (R4, tab 5.6 at 948), we find that contract performance was
characterized by repeated government-caused delays that aggregated to 263 days
and pushed the start work date into February 2010. The delays were chiefly caused
by the unavailability of new facilities for the existing tenants in building M403
(R4, tab 6 at 1107). The multiple delays to the start date were memorialized
as follows:
Date Document Start Date Record Citation
January 13, 2009 Solicitation 10 calendar days R4, tab 5.6 at 948
after award.
March 10, 2009 Solicitation âWork may not R4, tab 1 at 21
Amendment begin . . . until
No.