ASBCA 62221
Board: ASBCA
Agency: Navy
Appellant: Metro Machine dba General Dynamics NASSCO-Norfolk
Date: 2022-03-29
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Metro Machine dba General Dynamics ) ASBCA No. 62221
NASSCO-Norfolk )
)
Under Contract No. N00024-16-D-4408 )
APPEARANCES FOR THE APPELLANT: Michael J. Gardner, Esq.
Christopher M. OâBrien, Esq.
Greenberg Traurig LLP
McLean, VA
APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq.
Navy Chief Trial Attorney
Philip S. Lazarus, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE PROUTY
This appeal is about the overhaul of a guided missile destroyer that took longer than
the delivery order (DO) on the above-captioned contract (the contract) allowed for. The
long pole in the tent turned out to be the replacement of a davit and winch used to place a
small boat into the water from the deck of the destroyer and to pluck it out. The repair of
old parts and installation of new ones by appellant, Metro Machineâs (NASSCOâs),
subcontractor, Advanced Integrated Technologies (AIT), didnât go well and AIT had to
repair some of its work and its own subcontractor on the job wound up supplanting it at the
end. The work was thus completed late, providing the basis for the Navy to impose
liquidated damages, which it did and which NASSCO challenges here. 1 As the reader
might have surmised: NASSCO 2 blames the Navy for the davit problems, arguing that the
contractual requirement that it (AIT, actually) subcontract with the davitâs original
equipment manufacturer (OEM) for certain work made the Navy responsible for any
problems AIT had with the OEM and that when the OEM was not available, it was the
1
The parties elected to proceed under Board Rule 11, in which there is no hearing and we
decide the merits of this dispute on the basis of the written record.
2
The appeal here is not technically a pass-through claim by AIT since the challenged
liquidated damages were assessed against NASSCO; nevertheless, the advocacy
often reads as if it were being advanced by AIT (NASSCO is sometimes presented
in its briefs as an objective third party, rather than as an interested party to the
lawsuit). In any event, we refer to arguments as being made by NASSCO herein,
even if they appear to be advanced by AIT.
Navyâs responsibility to oversee AITâs work and save it from its own mistakes; the Navy
blames NASSCO and AIT. The Navy argues that this dispute was already largely resolved
by means of a bilateral change order which (says the Navy) constituted an accord and
satisfaction. Unfortunately for the Navy, the âbilateralâ change order in the record is signed
only by the Navy, effectively stopping this defense in its tracks. Nevertheless, the delays
were the responsibility of AIT and thus NASSCO, not the Navy. NASSCO has also
challenged the use of the liquidated damages clause that it had agreed to, but we find it to
have been proper.
FINDINGS OF FACT
I. Preliminaries: the Contract and the DO
A. The Contract
The contract at issue in this case is a multiple award task order contract
(MATOC) 3 for the maintenance, modernization, and repair (also referred to as âoverhaulâ
herein) of U.S. Navy warships (specifically, guided missile destroyers and cruisers) at the
Navyâs Mid-Atlantic Maintenance Center, located at Naval Station Norfolk in Norfolk,
Virginia (R4, tab 1.1 at GOV 1, GOV 18-19 4). It consisted of a base year and four option
years, and the DOs could be issued in either firm-fixed-price or cost-plus-fee varieties
(id. at GOV 2-10). The contract was awarded to NASSCO on February 17, 2016 (id.
at GOV 1).
One set of contract provisions sets forth procedures to follow if, in the midst of the
overhaul, the contractor finds more work that needs to be done on a ship than originally
planned for. That section in the Statement of Work begins in Section 3.0 and goes
through Section 3.5. (R4, tab 1.1 at GOV 22-23) Section 3.1, âIdentification of
Condition Found,â requires the contractor to notify the government of âneeded repairsâ
and to recommend corrective action for issues not identified in the original DO. It
specifies the contractor should make notification to the government within one day of
discovery, to be later followed by a more detailed âcondition found reportâ (CFR)
including the contractorâs recommendations. (Id.