CBCA 6760
Board: CBCA
Agency: General Services Administration
Appellant: Wu & Associates, Inc.
Date: 2022-12-22
Outcome: dismissed
GRANTED IN PART: December 22, 2022
CBCA 6760
WU & ASSOCIATES, INC.,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Sean T. OâMeara of Archer & Greiner, P.C., Voorhees, NJ, counsel for Appellant.
Jay Bernstein, Office of General Counsel, General Services Administration,
Washington, DC, counsel for Respondent.
Before Board Judges RUSSELL, SULLIVAN, and CHADWICK.
RUSSELL, Board Judge.
In a previous decision, the Board granted Wu & Associates, Inc.âs (Wu) motion for
partial summary judgment on entitlement upon finding that the specification at issue was
defective because using skids to strengthen flooring at a federal building to support the
weight of heavy elevator equipment was infeasible and that Wu relied on this defective
specification. Wu & Associates, Inc. v. General Services Administration, CBCA 6760,
21-1 BCA ¶ 37,965. Following the Boardâs decision, Wu and the General Services
Administration (GSA) agreed to brief the issue of quantum on the written record under Board
Rule 19, 48 CFR 6101.19 (2021), and the Board issued scheduling orders consistent with the
CBCA 6760 2
partiesâ agreement.1 After reviewing the record, we find that Wu has established entitlement
to some of its costs.
Background
In December 2018, during a site visit shortly after contract award, Wu determined that
the existing raised floor on the seventeenth floor of the Ted Weiss Federal Building in New
York City could not support the weight of heavy elevator equipment. Wu submitted a
change order request proposing to correct, protect, and strengthen the floor. The proposal
involved Hi Tech Data Floors, Inc. (Hi Tech), the original floor installer, removing the
existing flooring, which the change order request alleged was damaged, installing support
pedals, and adding an underlayment and new flooring. In March 2019, Wu notified GSA that
it would submit further information in support of the change order request. In April 2019,
Wu provided GSA a report prepared by William J. Madden (Mr. Madden), a professional
engineer, in which he concluded that the existing floor could not support the load of the
elevator equipment by only distributing the load.
GSA, GSAâs project manager, Wu, and KONE Elevators (KONE), the elevator
installer, continued to discuss the engineering needed to address the limited load capacity of
the floor. Wu submitted a formal proposal in early May 2019 with options to safely move
the elevator equipment, including the use of an elevator shaft to hoist the equipment up to
the machine room which Wu determined would be the most effective option. Relying upon
Mr. Maddenâs opinion, Wu noted that using skids over the floor to distribute the equipment
load, as required by GSA in the contract, would not work. GSA informed Wu that the
agency had no objection to Wuâs proposal, but it asked for additional technical details.
In response, Wu provided a detailed analysis prepared by Innova Technologies, Inc.
(Innova). Innova proposed the use of an âAir Sledâ system to move the elevator equipment
over the raised floor with a customized skid. Innova rejected the proposal to add more
stanchions because that solution might not be feasible since the space under the floor was
already being used for wiring. Innova also noted the possibility that the stanchions might fail
without a full understanding of the internal forces of the proprietary floor panel system, and
the process involving the installation of stanchions was labor-intensive. At a meeting in June
2019, GSA raised questions about the âAir Sledâ system proposal and instructed Wu to,
again, look into the possibility to reinforce the raised flooring panels with more stanchions.
1
See American Agri-Business Insurance Co., CBCA 4708-FCIC, 16-1 BCA
¶ 36,303, at 177,028 n.1 (treating the partiesâ motions for summary relief as submissions of
the case on the record consistent with the prior expressed intent of the parties and the Boardâs
order.).
CBCA 6760 3
GSA also asked Wu to provide a more scientific and engineering analysis on the raised
flooring and a scientific and detailed analysis on the âAir Sledâ system solution.
In September 2019, KONE, with PSP Enterprises, Inc. (PSP), an engineering
company, revisited the solution of reinforcing the raised floor.