CBCA 4594(3048)-REM-R
Board: CBCA
Appellant: Reliable Contracting Group, LLC
Date: 2016-01-14
MOTION FOR RECONSIDERATION DENIED: January 14, 2016
CBCA 4594(3048)-REM-R
RELIABLE CONTRACTING GROUP, LLC,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Reginald A. Williamson and William E. Dorris of Kilpatrick Townsend & Stockton
LLP, Atlanta, GA; and Gregory C. Thomas, General Counsel of Fisk Electric Company,
Houston, TX, counsel for Appellant.
Benjamin Diliberto and Charlma Quarles, Office of General Counsel, Department of
Veterans Affairs, Washington, DC, counsel for Respondent.
Before Board Judges DANIELS (Chairman), HYATT, and SHERIDAN.
SHERIDAN, Board Judge.
Appellant has filed a motion for reconsideration of the Boardâs decision in Reliable
Contracting Group, LLC v. Department of Veterans Affairs, CBCA 4594(3048)-REM, 15-1
BCA ¶ 36,114. Familiarity with that decision is presumed. For the reasons below, we deny
the motion.
Background
This appeal arose from a claim in which Reliable Contracting Group, LLC (Reliable)
sought additional costs for the Department of Veterans Affairsâ (VAâs) alleged rejection of
back-up emergency generators provided for a project at the VA medical center in Miami,
CBCA 4594(3048)-REM-R 2
Florida. The parties in this appeal elected, pursuant to Rule 19 of the Boardâs Rules of
Procedure, to submit the case for decision on the written record without a hearing. 48 CFR
6101.19 (2013).
The Board concluded that the generators, which had been in storage for four years,
could not be factory-tested and did not meet the requirement of being ânew.â We also found
that at the time the units were delivered, and the VA questioned whether the generators were
in compliance with the applicable contractual requirements, neither Reliable nor its electrical
subcontractor, Fisk Electric Company (Fisk), characterized the generators as ânewâ or
asserted that the units met the specification in response to the VAâs specific request for
confirmation that this was the case. Reliable Contracting Group, LLC v. Department of
Veterans Affairs, CBCA 3048, 14-1 BCA ¶ 35,475 (2013). Reliable appealed that decision.
The United States Court of Appeals for the Federal Circuit, in Reliable Contracting
Group, LLC v. Department of Veterans Affairs, 779 F.3d 1329, 1334 (Fed. Cir. 2015), held
that Reliable was required to install ânewâ generators and stated that this term meant that the
generators were to be in âfresh condition,â ânot . . . used,â and âfree of significant damage,
i.e., damage that was not cosmetic.â The Court vacated the Boardâs decision and remanded
the appeal to the Board with instructions âto determine whether the damage to the generators
during the four-year period between the original manufacture and the date of delivery to the
VA site was significant enough to render the generators not ânew.ââ Id. at 1335.
Following the remand, the Board issued another decision denying Reliableâs claim,
concluding, among other things, that there was insufficient evidence in the written record to
make a finding that the generators were ânewâ when they were delivered to the VA site and
that when the VA asked Reliable about the generators, both Reliable and Fisk characterized
the generators as unacceptable, were either unwilling or unable to represent the generators
as ânew,â abandoned the generators shortly after delivery, and only began arguing that the
generators should have been accepted approximately three years later when Reliable filed its
claim. Reliable, 15-1 BCA at 176,308-10. After the issuance of the decision Reliable filed
this motion.
In the motion Reliable reveals that after the remand, but prior to the Board issuing its
decision, the parties engaged in settlement negotiations. As a culmination of these settlement
negotiations, on September 15, 2015, the parties reached an agreed settlement amount of
â$550,000 âall inâ from Reliableâs claimed quantum of $1,138,662.95, plus CDA [Contract
Disputes Act] interest . . . shook hands on the deal, and committed to getting the paperwork
finalized as soon as possible.â Appellantâs Motion ¶¶ 10, 11.
CBCA 4594(3048)-REM-R 3
On September 16, 2015, respondentâs counsel sent appellantâs counsel a draft
settlement agreement. Appellantâs Motion ¶ 12. Over the next ten days respondentâs counsel
reviewed the draft settlement agreement with Fiskâs counsel and prepared a draft joint motion
for judgment on stipulation of settlement.