CBCA 2862
Board: CBCA
Agency: Smithsonian Institution
Appellant: Turner Construction Company
Date: 2017-05-05
Outcome: granted
THIS OPINION WAS INITIALLY ISSUED UNDER PROTECTIVE ORDER AND
IS BEING RELEASED TO THE PUBLIC IN ITS ENTIRETY ON
MAY 5, 2017
CBCA 2862 GRANTED IN PART; CBCA 4085, 4802 GRANTED: April 14, 2017
CBCA 2862, 4085, 4802
TURNER CONSTRUCTION COMPANY,
Appellant,
v.
SMITHSONIAN INSTITUTION,
Respondent.
Douglas L. Patin and Michael S. Koplan of Bradley Arant Boult Cummings LLP,
Washington, DC, counsel for Appellant.
Scott D. Cessar of Eckert Seamans Cherin & Mellott, LLC, Pittsburgh, PA, counsel
for Subcontractor March-Westin Company.
Lawrence M. Prosen and Christian F. Henel of Kilpatrick Townsend & Stockton,
LLP, Washington, DC, counsel for Subcontractors Welch and Rushe, Inc. and M.C. Dean,
Inc.
Roger C. Jones of Huddles Jones Sorteberg & Dachille, P.C., Columbia, MD, counsel
for Subcontractors Stromberg Metal Works, Inc. and Apro Enterprises, Inc.
Robert Windus of Moore & Lee, LLP, McLean, VA, counsel for Subcontractor C.J.
Coakley Co., Inc.
CBCA 2862, 4085, 4802 2
Craig A. Holman and Kara L. Daniels of Arnold & Porter Kaye Scholer LLP,
Washington, DC, counsel for Respondent.
Before Board Judges KULLBERG, SULLIVAN, and CHADWICK.1
SULLIVAN, Board Judge.
Appellant, Turner Construction Company (Turner), filed three appeals from
contracting officer decisions issued by respondent, the Smithsonian Institution (Smithsonian
or SI), concerning matters arising on its contract to provide design and construction services
in a long-term, multiple-phase project entitled âPublic Space Renewal Project at the National
Museum of American History.â Turner Construction Co. v. Smithsonian Institution, CBCA
2862, 13 BCA ¶ 35,290, at 173,252; see Turner Construction Co. v. Smithsonian Institution,
CBCA 2862 et al., 15-1 BCA ¶ 36,139, at 176,388.
Turnerâs first appeal (docketed as CBCA 2862) was of the contracting officerâs
decision denying its claim for approximately $14 million, which included Turnerâs claim for
general conditions costs of approximately $7 million and subcontractor claims for delay and
disruption costs of approximately $7 million. In an initial ruling, the Board held that the
parties had failed to agree upon a firm fixed price for the base contract work to be performed
by Turner and that Turner was entitled to be paid a reasonable price for that work. Turner
Construction, 13 BCA at 173,260.
Following that initial ruling, Smithsonian conducted an audit of all the costs incurred
by Turner on the project. Based solely upon the results of that audit, the contracting officer
issued a second decision, finding that Turner had been overpaid by approximately $40
million. To effect repayment, the contracting officer denied Turnerâs claim in its entirety and
asserted a claim for an additional $24.5 million paid to Turner on the contract. Turner also
appealed that decision to the Board, docketed as CBCA 4085.
Turner filed a second claim in 2015, seeking costs of approximately $440,000 that it
incurred to install a second steam generator in the museum. The contracting officer denied
Turnerâs claim, and Turner appealed, docketed as CBCA 4802. The second and third appeals
were consolidated with the first appeal when they were filed.
1
When the first appeal was filed, a panel composed of Judges Somers, McCann,
and Kullberg was assigned to hear these appeals. The matter was transferred to Judge
Sullivan on December 17, 2014. Upon the retirement of Judge McCann, Judge Walters was
assigned to the panel. Upon the retirement of Judge Walters, Judge Chadwick was assigned
to the panel.
CBCA 2862, 4085, 4802 3
The contract between Turner and Smithsonian, by its terms, is not subject to the
Contract Disputes Act (CDA). 41 U.S.C.§§ 7101-7109 (2012). Exhibit 1_F at 320.2
Instead, the Disputes clause of the contract provides that a contractor may appeal a
contracting officerâs decision to the Secretary of the Smithsonian Institution. Id. at 321. By
memorandum of agreement between Smithsonian and the Board, dated June 5, 2012, the
Board agreed to hear and decide the appeals arising from this contract. Turner Construction,
13 BCA at 173,258.
The Board conducted a hearing in November 2015. The Board heard testimony from
thirty witnesses over fourteen days.