CBCA 7759
Board: CBCA
Agency: General Services Administration
Appellant: Lusk Mechanical
Contractors, Inc.
Date: 2024-04-30
Outcome: denied
DENIED: April 30, 2024
CBCA 7759
LUSK MECHANICAL CONTRACTORS, INC.,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Thomas E. Roma, Jr. of Manion Stigger LLP, Louisville, KY, counsel for Appellant.
James Scott, Office of General Counsel, General Services Administration,
Washington, DC, counsel for Respondent.
Before Board Judges BEARDSLEY (Chair), GOODMAN, and KULLBERG.
BEARDSLEY, Board Judge.
This appeal arose from a contract between the appellant, Lusk Mechanical
Contractors, Inc. (Lusk), and the General Services Administration (GSA) for a construction
project in St. Croix, United States Virgin Islands (USVI). Lusk avers that it is entitled to an
$839,616 equitable adjustment under the Federal Acquisition Regulation (FAR) Suspension
of Work clause. 48 CFR 54.242-14 (2023) (FAR 54.242-14). We deny the appeal.
CBCA 7759 2
Background
In December 2019, the parties entered into a contract for $13,330,334 (later increased
to $13,959,314) for “construction services to repair, replace, and/or modernize site/building
elements and building systems” at the Almeric L. Christian Federal Building and United
States Courthouse (the project) in St. Croix. Appeal File, Exhibit 1 at 19.1 The contract
work required Lusk to
provid[e] all labor, materials, tools and equipment necessary to replace all
exterior lighting, replace the roof skylight, replace the roof gutter, modernize
all elevators, replace all exterior windows, window shutters and interior glass
and wood doors, upgrade the security fence, replace a full load generator and
increase fuel tank capacity, replace chilled water piping insulation, and install
a new well and domestic water filtration/treatment plant as well as associated
work in mechanical, electrical and plumbing, as indicated on the drawings
including all phasing and sequencing, as noted in the general and supplemental
general conditions and general project requirements of Division 1.
Id. The construction services were to be completed “while maintaining continuous operation
of the existing building.” Id. The contract included Lusk’s contract pricing form, which
included a $9600 “Daily Rate for Compensable Project Delay (Work Day),” id. at 7, and
called for substantial completion of some tasks 199 days from the issuance of the notice to
proceed and for other tasks 541 days from the issuance of the notice to proceed. Id. at 21.
Among other provisions, the contract incorporated FAR clause 52.242-14, Suspension
of Work (APR 1984). Exhibit 1 at 67. The clause, in relevant part, reads as follows:
(a) The Contracting Officer may order the Contractor, in writing, to suspend,
delay, or interrupt all or any part of the work of this contract for the period of
time that the Contracting Officer determines appropriate for the convenience
of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable
period of time, suspended, delayed, or interrupted . . . by an act of the
Contracting Officer . . . an adjustment shall be made for any increase in the
cost of performance of this contract (excluding profit) necessarily caused by
the unreasonable suspension. . . . However, no adjustment shall be made under
1
All exhibits are found in the appeal file, unless otherwise noted.
CBCA 7759 3
this clause for any suspension . . . to the extent that performance would have
been so suspended . . . by any other cause.
FAR 54.242-14.