CBCA 7269
Board: CBCA
Agency: Department of Transportation
Appellant: JITA Contracting, Inc.
Date: 2025-03-24
Outcome: denied
APPELLANTâS MOTION FOR SUMMARY JUDGMENT DENIED;
RESPONDENTâS MOTION FOR SUMMARY JUDGMENT GRANTED IN PART:
March 24, 2025
CBCA 7269, 7675, 7784, 7898, 7899, 7900, 7919, 8022
JITA CONTRACTING, INC.,
Appellant,
v.
DEPARTMENT OF TRANSPORTATION,
Respondent.
Ivan A. Sarkissian and Nathaniel Rioux Jordan of McConaughy & Sarkissian, P.C.,
Denver, CO, counsel for Appellant.
Jack F. Gilbert and Emma R. Vyncke, Office of Chief Counsel, Federal Highway
Administration, Department of Transportation, Lakewood, CO, counsel for Respondent.
Before Board Judges BEARDSLEY (Chair), SULLIVAN, and CHADWICK.
CHADWICK, Board Judge.
A subagency of respondent, Department of Transportation (DOT), terminated for
default a road construction contract with appellant, JITA Contracting, Inc. (JITA). In these
eight consolidated appeals, JITA challenges the termination and seeks delay damages and the
return of amounts withheld for delay. Both parties move for summary judgment. We grant
DOTâs motion in part and otherwise deny the motions.
CBCA 7269, 7675, 7784, 7898, 7899, 7900, 7919, 8022 2
We reject JITAâs argument that the default termination was invalid because DOT lost
its right to enforce the completion date in the contract. We rejectâlargely as unsupported
by citations to record evidenceâDOTâs arguments for summarily sustaining its termination
claim and for denying JITAâs claims based on project delay. We agree with DOT, however,
that the contract included price disincentives for failure to meet an interim completion date,
so we grant DOTâs motion to that limited extent.
Background
We deem the following facts to be undisputed based on the amended statements of
undisputed material facts, amended statements of genuine issues, and record evidence cited
in those filings. See Board Rule 8(f)(1), (2) (48 CFR 6101.8(f)(1), (2) (2023)); Avue
Technologies Corp. v. Department of Health & Human Services, CBCA 8087(6360)-REM,
et al., 24-1 BCA ¶ 38,617, at 187,709 n.1.1
JITA and the Federal Highway Administration, a DOT component, executed the
contract for road work in Mesa Verde National Park in Colorado on February 4, 2021. The
contract divided the work into schedule A (the primary work) and three awarded options.
The completion date for the schedule A work, reconstructing a roadway âloop,â was June 15,
2021. Work on at least one of the options could not begin until the primary work was
finished, and all work including the options was to be completed by September 6, 2021. The
contract contained provisions for weather delays, but the parties do not direct us to any
indication that the work was limited to certain seasons of the year.
The contract included both âdisincentive deductionsâ from the contract price if JITA
did not timely complete the schedule A work and a table of graduated âliquidated damagesâ
1
Consistent with Avue Technologies, we disregard unexplained demurrals in the
statements of genuine issues. DOT, for example, ârefers the Boardâ generally âto the plans
and specificationsâ as clarifying evidence. We will not search the exhibits and guess what
DOT means. â[I]t is the duty of counsel, not the Board, to advocate for their respective
clients.â Lebolo-Watts Constructors 01 JV, LLC, ASBCA 59740, et al., 21-1 BCA ¶ 37,789,
at 183,426 (2020), affâd, No. 21-1749, 2022 WL 499850 (Fed. Cir. Feb. 18, 2022). We also
disregard exhibits to DOTâs amended statement of genuine issues that are not Rule 4 appeal
file exhibits. The Board ordered in March 2022 that â[s]tatements filed under Rule 8(f)(1)
and (2) shall cite appeal file exhibits rather than separate exhibits attached to briefs, except
for deposition excerpts. This may require a movant to coordinate its supplementation of the
appeal file with the drafting of its motion.â (Emphasis omitted.)
CBCA 7269, 7675, 7784, 7898, 7899, 7900, 7919, 8022 3
starting at $1600 per day for late completion of the entire contract.2 The contract referred to
the schedule A completion date as âan interim completion date.â It further stated: âFailure
to substantially complete the work within the timeframe described below [the June 15, 2021,
interim completion date] will result in the assessment of disincentives at a rate of $2,700 per
calendar day. If Schedule A only is awarded, the disincentive deductions will be in addition
to any Contract administration liquidated damages.â
The agency issued the notice to proceed on or about March 8, 2021.