ASBCA 62928
Board: ASBCA
Agency: Army Corps of Engineers
Appellant: Jemison & Partners, Inc.
Date: 2022-11-29
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Jemison & Partners, Inc. ) ASBCA No. 62928
)
Under Contract No. W912P8-19-C-0018 )
APPEARANCE FOR THE APPELLANT: W. Lee Kohler, Esq.
Kohler Construction Law, APLC
Metairie, LA
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
William G. Meiners, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, New Orleans
OPINION BY ADMINISTRATIVE JUDGE OâCONNELL
This is a dispute about topsoil, or, more specifically, a dispute about whether
appellant would be paid for the actual quantities of soil placed, or simply a lump sum.
Appellant seeks $53,104.80. The parties waived a hearing and submitted the appeal on
the record under Board Rule 11. The Board denies the appeal.
FINDINGS OF FACT
1. The parties entered into the above-captioned contract for greenspace
restoration on February 15, 2019. The work included the replacement of topsoil and
the planting of sod and trees along the median of Jefferson Avenue in Orleans Parish,
Louisiana at a price of $747,298.57. (R4, tab 9 at 1, 3-5, 39, 44) 1
2. The Corps issued the solicitation on November 16, 2018 (R4, tab 4 at 1).
The bid schedule for the solicitation listed an âestimated quantityâ of 2,355 cubic
yards (CY) of topsoil and requested unit price bids, which would result in an
âestimated amountâ for that contract line item number (CLIN 0002). Note 1 to the bid
schedule provided that:
The Contractor shall verify all quantities on the plan;
quantities are provided as an aid to bidders only.
1
Rule 4 citations are to the .pdf page number in the electronic file.
Quantity takeoff mistakes made by the Contractor shall
be no cause for additional costs to the Government.
(R4, tab 4 at 8) (emphasis in original) The bid schedule, with Jemisonâs bid numbers,
was included in the contract but the word âestimatedâ was omitted from the column
heading so that âEstimated Quantityâ became âQTYâ and âEstimated Amountâ
became âTotal Amount.â Note 1, however, was included in the contract (R4, tab 9
at 41).
3. The Standard Form 1449 Continuation Sheet in the solicitation (and the
contract) identified CLIN 0002 as âFFPâ or firm-fixed price (R4, tab 4 at 3; tab 9 at 3).
The Board finds that a reasonably prudent bidder would have understood from reading
the Continuation Sheet in conjunction with the Bid Schedule that the price per CY was
fixed but the quantity of topsoil was an estimate.
4. The Payment Procedures section of the solicitation, at Section 1.4, Payments
to the Contractor, required the submission of invoices and âquantity backup data by
the [c]ontractor,â and provided that upon initial site work acceptance Jemison would
be paid â100% contract cost for topsoilâ (R4, tab 4 at 15). This provision was
included in the contract (R4, tab 9 at 48).
5. The Excavation and Fill section of the solicitation at Part 4, Measurement
and Payment, provided:
Measurement for work required under this section shall be
an in place topsoil cubic yard measurement. The topsoil
quantities are provided as an aid to bidders only. The
contractor shall take measurements subtracting rootball
volume at each area requiring excavation and soil
replacement. . .
(R4, tab 4 at 34, 43) This provision was included in the contract (R4, tab 9 at 76).
6. Jemison submitted various questions to the Corps during negotiation of the
contract. The Corps answered a question from Jemison related to the topsoil in an
amendment to the solicitation issued on January 28, 2019:
Q1. . . . [C]an we retain the same estimated quantities for
top soil and add a qualification in the revised proposal that
the actual quantities utilized will be verified by the
USACE in the field? It is our understanding the USACE
carefully confirms material quantities (such as top soil) in
the field as work progresses. We understand that the
2
USACE will only pay for verified materials used in the
project.
A1. . . .