ASBCA 58242
Board: ASBCA
Date: 2014-05-14
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
MIC/CCS, Joint Venture ) ASBCA No. 58242
)
Under Contract No. F42650-03-D-0010 )
APPEARANCES FOR THE APPELLANT: Richard C. Johnson, Esq.
John S. Pachter, Esq.
Smith Pachter Mc Whorter PLC
Vienna, VA
Patrick Hendrickson, Esq.
Hendrickson Law Firm
South Jordan, UT
APPEARANCES FOR THE GOVERNMENT: Col Robert J. Preston II, USAF
Acting Air Force Chief Trial Attorney
Jeffrey M. Lowry, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE SCOTT
ON APPELLANT'S MOTION FOR SUMMARY JUDGMENT
MIC/CCS, Joint Venture (MIC/CCS) has appealed under the Contract Disputes
Act (CDA), 41 U.S.C. §§ 7101-7109, from the contracting officer's (CO's) termination
of Delivery Order (DO) No. 0383 under the subject contract for default. It moves for
summary judgment, converting the default termination to one for convenience, on the
basis that the government waived the DO's completion date and appellant was excusably
delayed through the termination date. The government opposes. At appellant's request,
the Board heard oral argument. For the reasons stated below we deny the motion.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 1
1. On 31 March 2003, pursuant to a Simplified Acquisition of Base Engineering
Requirements (SABER) solicitation, the Air Force awarded negotiated Contract
No. F42650-03-D-0010, a multiple award Indefinite Delivery, Indefinite Quantity section
1
Appellant presents additional proposed facts (PF) in its redacted 14 June 2013
response to the Air Force's opposition to its motion for summary judgment (app.
resp.). We have reviewed them but do not find them necessary to our resolution of
the motion.
8(a) set-aside contract for design and construction services at Hill Air Force Base (AFB),
Utah, and other sites, to MIC/CCS for a one-year base period with seven option years
(R4, tab 1at1-6of33, Description of Work at 5).
2. The contract incorporates by reference or contains numerous Federal
Acquisition Regulation (FAR) clauses, including the following:
FAR 52.211-12, LIQUIDATED DAMAGES - CONSTRUCTION (SEP 2000), which
provides that if the contractor fails to complete the work in the time specified, it "shall
pay liquidated damages to the Government in the amount of $162.00 for each calendar
day of delay until the work is completed or accepted" (R4, tab 1at10 of33).
FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEP
2002) (R4, tab 1 at 15), which provides in part that the government is to "make progress
payments monthly as the work proceeds ... on estimates of work accomplished which
meets the standards of quality established under the contract, as approved by the [CO]."
FAR 52.233-1, DISPUTES (JUL 2002)-ALTERNATE I (DEC 1991) (R4, tab 1at15
of 33), which provides in part:
(i) The Contractor shall proceed diligently with
performance of this contract, pending final resolution of any
request for relief, claim, appeal, or action arising under or
relating to the contract, and comply with any decision of the
[CO].
FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) (R4, tab 1at15), which
provides that the CO is to investigate promptly after receiving notice from the contractor
of alleged differing site conditions and, if there are such conditions as defined in the
clause, and they cause an increase in the contractor's cost of, or time to perform, the
work, an equitable contract adjustment is to be made.
FAR52.249-10,DEFAULT(FIXED-PRICECONSTRUCTION)(APR 1984)(R4, tab 1 at
15), which provides in part:
(a) If the Contractor refuses or fails to prosecute the
work or any separable part, with the diligence that will insure
its completion within the time specified in this contract
including any extension, or fails to complete the work within
this time, the Government may, by written notice to the
Contractor, terminate the right to proceed with the work (or
the separable part of the work) that has been delayed~...