ASBCA 59610
Board: ASBCA
Date: 2014-10-23
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of-- )
)
Environmental Safety Consultants, Inc. ) ASBCA No. 58343
)
Under Contract No. N62470-95-C-2399 )
APPEARANCE FOR THE APPELLANT: Mr. Peter C. Nwogu
President
APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq.
Navy Chief Trial Attorney
Ellen M. Evans, Esq.
Senior Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE FREEMAN ON
THE GOVERNMENT'S RENEWED MOTION TO DISMISS
On 10 July 2014, the government submitted this renewed motion to dismiss the
appeal on the grounds that (i) Environmental Safety Consultants, Inc., (ESCI) has not
complied with the Board's 20 May 2014 discovery order, and (ii) ESCI's failure to
retain cost records as required by the contract has prejudiced the government's ability
to respond to ESCI' s allegations in the appeal. ESCI opposes the motion stating that
(i) it provided its books and records for government inspection as required by FAR and
(ii) the fact that its books and records did not contain evidence of actual incurred costs
was no basis for dismissing the appeal or applying sanctions (opp'n at 9). On review
ofESCI's responses to the discovery order, we find substantial non-compliances
which warrant prohibiting ESCI from producing at hearing any documentary evidence
or witness that should have been disclosed in the discovery ordered by the Board.
Accordingly, that sanction is ordered and the motion to dismiss is denied.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. The captioned contract, awarded on 13 November 1995, (hereinafter
"Contract 2399") was terminated for default on 12 June 1998. On 28 September 2011,
the Board sustained an appeal from the default termination. Pursuant to the terms of
the contract, that decision converted the default termination to a termination for the
convenience of the government. See Environmental Safety Consultants, Inc., ASBCA
No. 51722, 11-2 BCA ~ 34,848. Familiarity with that decision is presumed.
2. On or about 5 July 2012, ESCI's submitted to the contracting officer a total
cost basis termination settlement proposal with a net payment request of$1,183,366.59
for the termination of Contract 23 99. On 14 September 2012, ESCI converted the
proposal to a claim under the Contract Disputes Act of 1978 (CDA), 41 U.S.C.
§§ 7101-7109. The contracting officer refused to either negotiate a settlement
agreement or issue a final decision on the claim. She alleged that the claim was
"conceived in fraud and is permeated by fraud" and that the contracting officer "lacks
authority to decide it or settle it." See Environmental Safety Consultants, Inc.,
ASBCA No. 58343, 14-1BCAif35,681 at 174,666. On 29 September 2012, ESCI
appealed the deemed denial of its claim, and that appeal (ASBCA No. 58343) is
presently before us.
3. The Federal Acquisition Regulation (FAR) 52.249-2, TERMINATION FOR
CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE}-ALTERNATE 1(APR1984) clause
(hereinafter "the Termination clause"), of the captioned contract states in pertinent
part:
(f) If the Contractor and Contracting Officer fail to
agree on the whole amount to be paid the Contractor
because of the termination of work, the Contracting Officer
shall pay the Contractor the amounts determined as
follows ...
( 1) For contract work performed before the
effective date of termination, the total (without duplication
of any items) of -
(i) The cost of this work;
(h) The cost principles and procedures of Part 31 of
the Federal Acquisition Regulation, in effect on the date of
this contract, shall govern all costs claimed, agreed to, or
determined under this clause.
4. The FAR 31.201-1, "Composition of total cost" provision, in effect on the
date of Contract 23 99, stated in pertinent part: "(a) The total cost of a contract is the
sum of the direct and indirect costs allocable to the contract, incurred or to be incurred,
less any allocable credits," plus any allocable cost of money pursuant to 31.205.10.
2
5.