CBCA 5361
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: HAL-PE Associates Engineering Services, Inc.
Date: 2018-03-14
Outcome: granted
GRANTED: March 14, 2018
CBCA 5361
HAL-PE ASSOCIATES ENGINEERING SERVICES, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Nancy M. Camardo of Camardo Law Firm, P.C., Auburn, NY, counsel for Appellant.
Mary A. Mitchell, Office of General Counsel, Department of Veterans Affairs,
Houston, TX; and Donald C. Mobly, Office of General Counsel, Department of Veterans
Affairs, Denver, CO, counsel for Respondent.
GOODMAN, Board Judge.
Appellant, Hal-Pe Associates Engineering Services, Inc., alleges it is due
compensation for extra work it performed in addition to the requirements of a construction
contract with respondent, Department of Veterans Affairs (VA).
Appellant elected to have this appeal processed under Board Rule 52, Small Claims
Procedure (48 CFR 6101.52 (2011)). Under the small claims procedure, â[t]he presiding
judge may issue a decision, which may be in summary form, orally or in writing. . . . A
decision shall be final and conclusive and shall not be set aside except in the case of fraud.
A decision shall have no value as precedent.â Rule 52. The parties also elected to have this
appeal processed under Board Rule 19, Submission on the Record Without a Hearing.
CBCA 5361 2
Background
Appellant was awarded contract no. VA250-14-C-0061 by respondent for
Remediation of Electrical Harmonics at the Veterans Affairs Ambulatory Care Center in
Columbus, Ohio. Appellant alleges that it completed all the known requirements by January
30, 2015.
Respondent alleged that the project was not completed for a number of reasons
including appellantâs failure to collect post-installation data for the harmonic correction units
which appellant installed. By cure notice dated April 8, 2015, respondent alleged that
appellant had not provided the post-installation data for the units that would have been
compiled from a metering that should have occurred for thirty days after installation.
On April 10, 2015, appellant responded to the cure notice, alleging that the post-
installation monitoring was not required by the contract. Appellant and respondent
communicated about the issue, and appellant ultimately performed the alleged extra work
under protest.
On March 1, 2016, appellant filed a claim for equitable adjustment, demanding
compensation in the amount of $7272.17 for the costs expended in performing the alleged
extra work. The contracting officer did not issue a final decision within the time required by
the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109 (2012), and appellant filed this
appeal from a deemed denial of the claim.
Discussion
During the proceedings in this appeal, respondent was directed to identify the
provisions in the contract that respondent alleges required appellant to perform the work for
which appellant seeks additional compensation. Respondent replied with various references
to portions of the contract that allegedly âindicateâ that the work in dispute was required, or
alternatively show that respondent âexpectedâ that the work would be performed.
The portions of the contract cited by respondent refer to power metering of harmonic
distortion to be performed in advance of filter installation, but not again at the completion
of the work as ultimately required by respondent. While the specifications state that âit is the
goal of this project to verify that all overcurrent devices are properly set per the original
design documents for selective coordination as required by the drawings and specifications,â
this is not a clear requirement for power metering and collection of data for thirty days after
installation as alleged by respondent. The contractual references relied upon by respondent
CBCA 5361 3
do not support its position that the work at issue was required by the contract. Appellant is
therefore entitled to compensation for the work performed.
Appellantâs claim details the costs allegedly incurred to perform the workâlabor,
subcontractor costs, indirect cost, profit, and contract administration. Respondent has offered
no analysis, rebuttal, or other evidence to question the incurrence or reasonableness of the
costs.