ASBCA 60515
Board: ASBCA
Agency: Army
Appellant: American Boys Construction Company
Date: 2017-09-13
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
American Boys Construction Company ) ASBCA No. 60515
)
Under Contract No. W56SGK-16-C-0013 )
APPEARANCE FOR THE APPELLANT: Mr. Nadeem Alamyar
President
APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.
Army Chief Trial Attorney
MAJ Bruce L. Mayeaux, JA
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE PROUTY
This appeal is about the compensation due to appellant, American Boys
Construction Company (ABC), for the government's terminating the above-captioned
contract (the contract) for convenience. ABC alleges 1 that in the nine days between
contract award and a government stop-work order, it incurred $67,793 in compensable
costs under the contract- primarily for supplies that it obtained in preparation for
contract performance, but also for stand-by labor costs (app. hr. at 2; app. reply br.;
see also R4, tab 10 at 4). 2 Because we find that ABC's purchase of the materials for
which it now seeks compensation was unreasonably premature and that the amounts
sought for stand-by labor costs have not been substantiated, we deny this appeal,
although we would have been open to some stand-by labor costs if only ABC had
presented evidence of such costs.
1
After initially requesting that this appeal proceed via a hearing, appellant ultimately
elected to proceed under the auspices of Board Rule 11, in which the appeal is
decided exclusively upon the written record.
2
ABC's briefs do not specify the amount of money sought in this appeal, nor does its
complaint or any other filing made with the Board, except that its reply brief
stated that it was seeking the amount requested by the termination settlement
proposal it submitted to the contracting officer (app. reply hr. at 4). That
amount was $67,793 (R4, tab 10 at 4).
FINDINGS OF FACT
On 14 February 2016, the government's Regional Contracting Center- Capital
in Kabul, Afghanistan (RCC), awarded the contract at issue in this appeal to ABC (R4,
tab 1 at 1-2). This firm-fixed-price contract in the amount of$120,801 ($113,301 for
the actual performance; $7,500 (estimated) for Defense Base Act Insurance) was for
the installation of a "sniper screen" at a base in Kabul (id. at 3). The contract's 60-day
period of performance was set to begin on 28 February 2016 and conclude on 29 April
2016. ABC was required to commence work within 5 days of receiving the notice to
proceed from the government. (Id. at 6)
On 17 February 2016, ABC's project manager, Mr. Walusimbi John, emailed
Sergeant First Class (SFC) Brandon Cooper, the contracting specialist assigned to
provide administrative support on the contract (app. supp. R4, tab 1 at 2)3 ⢠Mr. John
said that he had "attached [a] list of suppliers for the project." SFC Cooper responded
by informing Mr. John that he was looking forward to working with him again, but that
the email included no attachment (id. at 3). The record does not indicate whether ABC
responded with a re-sent attachment, and, given the email sent by ABC to SFC Cooper
three days later (discussed below), we think it unlikely that it did.
On 18 February 2016, four days after contract award, the government held a
preconstruction conference as provided for by the contract (see R4, tab 1 at 15
(contractual provision incorporating Federal Acquisition Regulation (FAR) 52.236-26,
PRECONSTRUCTION CONFERENCE (FEB 1995) into the contract), tab 2 (signed
memorandum detailing conference)). According to a memorandum describing the
conference that was signed by both government and ABC representatives, among
other matters discussed, ABC was informed of the contractual requirement to tender
material submittals to the government on a specified form, the Air Force Form 3000
(R4, tab 2 at 2-3). Government representatives who attended this meeting included
Major (MAJ) Joseph Cederstrom (the contracting officer (CO)), SFC Cooper,
and First Lieutenant (lLT) David Morin (the CO's technical representative) (R4,
tabs 14-16). SFC Cooper provided written testimony that, although he did not
specifically recall the discussion held during this meeting, the standard practice at all
such meetings he attended in Afghanistan was to follow the agenda set forth in the
3
ABC submitted to the Board, on 14 February 2017, a number of documents to act as
its supplement to the Rule 4 file.