CBCA 7661
Board: CBCA
Agency: Department of State
Appellant: Framaco International Inc.
Date: 2023-09-22
Outcome: dismissed
THIS OPINION WAS INITIALLY ISSUED UNDER PROTECTIVE ORDER AND
IS BEING PUBLICLY RELEASED IN ITS ENTIRETY ON OCTOBER 5, 2023
RESPONDENTâS MOTION TO DISMISS GRANTED;
APPELLANTâS REQUEST FOR DECLARATORY RELIEF DENIED:
September 22, 2023
CBCA 7661
FRAMACO INTERNATIONAL INC.,
Appellant,
v.
DEPARTMENT OF STATE,
Respondent.
Douglas L. Patin and Erik M. Coon of Bradley Arant Boult Cummings LLP,
Washington, DC; and Sam Z. Gdanski and Abraham S. Gdanski of Gdanski Law PC,
Teaneck, NJ, counsel for Appellant.
Thomas D. Dinackus, Office of the Legal Adviser, Buildings and Acquisitions,
Department of State, Washington, DC, counsel for Respondent.
Before Board Judges BEARDSLEY (Chair), RUSSELL, and OâROURKE.
RUSSELL, Board Judge.
Appellant, Framaco International Inc. (Framaco), has filed 119 appeals with the
Board (twenty-three of which are consolidated), based on its contract with respondent,
Department of State (State), Bureau of Overseas Building Operations (OBO), to construct
an embassy compound in Port Moresby, Papua New Guinea. This appeal (CBCA 7661)
CBCA 7661 2
results from Stateâs denial of Framacoâs claim that requested a contracting officerâs final
decision (COFD) declaring that the agency breached the partiesâ contract (1) by the
contracting officer (CO) failing to issue a decision, favorable to Framaco, on one of
Framacoâs claims and (2) by the CO failing to exercise personal and independent judgment
in issuing decisions under the contract. Framaco asserts that a favorable decision in this
appeal âwill eliminate the need for the parties to litigate, and for this Board to decide, all the
other . . . pending appeals given the breach of contract damages Framaco would be entitled
to recover under well-established authority.â Appellantâs Reply to Respondentâs Opposition
to Appellantâs Motion to Expedite CBCA 7661 and Stay Related Proceedings and Opposition
to Respondentâs Motion to Dismiss (Appellantâs Reply) at 3.
State has moved to dismiss this appeal, arguing that the appeal is essentially one for
monetary relief for which Framaco, in its underlying claim before the agency, provided
neither a sum certain nor the certification required by the Contract Disputes Act (CDA),
41 U.S.C. §§ 7101â7109 (2018). Alternatively, State moves to dismiss this appeal on
prudential grounds for a number of reasons, including that the CDA would adequately
provide Framaco with any relief to which it is entitled assuming a finding of liability.
On September 13, 2023, the Board held a hearing on Framacoâs non-consolidated or
small claims appeals. For reasons stated at that hearing and below, we decline to grant
declaratory relief to Framaco and dismiss the appeal.
Background
A. The Contract
In July 2015, State awarded Framaco a firm-fixed-price contract, initially valued at
$96,875,381, to construct the New Embassy Compound (NEC) in Port Moresby, Papua New
Guinea. Appeal File (CBCA 6997, et al.), Exhibit 1 at DOS-PTMO-00982321.1 The project
was originally designed in 2010 as a âStandard Secure mini-Compoundâ (SSmC) with a
scope including a lock-and-leave new office building, a perimeter security wall and fence,
a main compound entry pavilion (MCAP), and a service entry/utility building and support
annex. Exhibit 2 at DOS-PTMO-00982414. Construction of the facility began in 2012, but
in 2013, after forty percent of the project was completed, a future marine detachment was
planned for Port Moresby and the embassy staffing requirement was increased. Id. State
therefore descoped the work under the 2012 contract and closed out that contract. The
project was redesigned under an expanded NEC, incorporating the completed portions of the
1
All exhibits are found in the appeal file of CBCA 6997, et al., which concerns
the same contract, unless otherwise noted.
CBCA 7661 3
SSmC project as well as surplus equipment and materials, where appropriate. Id. The
redesigned project included the perimeter security wall and fence, the MCAP, a new service
compound entry pavilion, a new four-story office building, a marine service guard residence,
a service entry/utility building, an enlarged support annex, and a new recreation facility.