CBCA 4377
Board: CBCA
Appellant: Suffolk Construction Company, Inc.
Date: 2016-08-26
MOTION TO DISMISS DENIED: August 26, 2016
CBCA 4377
SUFFOLK CONSTRUCTION COMPANY, INC.,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
James R. Newland, Jr., and Anthony J. LaPlaca of Seyfarth Shaw, LLP, Washington,
DC, counsel for Appellant.
James F.H. Scott and Justin S. Hawkins, Office of General Counsel, General Services
Administration, Washington, DC; and Nancy E. OâConnell and Meaghan Q. LeClerc, Office
of Regional Counsel, General Services Administration, Boston, MA, counsel for
Respondent.
Before Board Judges SOMERS, WALTERS, and ZISCHKAU.
ZISCHKAU, Board Judge.
On December 5, 2014, the Court of Federal Claims (COFC) issued an order
transferring to the Board an action filed at the COFC on April 25, 2014, by Suffolk
Construction Company, Inc. (Suffolk), challenging a General Services Administration (GSA)
contracting officerâs final decision. Suffolk Construction Co. v. United States, No. 12-350C
(Fed. Cl. Dec. 5, 2014) (transfer order). GSA at the time concurred in the transfer. The
transferred action was docketed at the Board as CBCA 4377 and consolidated with six other
appeals Suffolk had previously filed with the Board relating to different claims but involving
CBCA 4377 2
the same contract. GSA recently filed a motion to dismiss CBCA 4377, asserting that the
Board lacks jurisdiction over the appeal because Suffolk did not initiate its action at the
COFC within ninety days of receipt of the contracting officerâs final decision. For the
reasons stated below, we deny GSAâs motion to dismiss.
Background
In 2001, Suffolk and GSA entered into contract no. GS01P05BZC3010 (the contract)
for the renovation of the John W. McCormack Building, a twenty-two story âhistoric art deco
structureâ located in Boston, Massachusetts. Complaint ¶¶ 10, 31; Answer ¶¶ 10, 31. This
firm-fixed-price contract was awarded for $136,153,445 and had a period of performance
from October 1, 2006, to April 16, 2009. Complaint ¶ 34; Answer ¶ 34.
Under the contract, Suffolk was to renovate the building with an emphasis on
âenvironmental sustainability and historic preservation.â Complaint ¶ 32; Answer ¶ 32.
Suffolk renovated the buildingâs existing entrances, lobbies, stairways, fixtures, libraries, and
courtrooms. Complaint ¶ 35. Suffolk also abated hazardous materials, modernized elevator
systems, refurbished finishes, accommodated new tenant spaces, and removed existing
mechanical and electrical systems. Id. ¶ 36.
Suffolkâs Appeals to the Board
Following the completion of the contract, Suffolk submitted a number of claims to
GSAâs contracting officer (CO) for the contract and appealed six of the COâs final decisions
to the Board.
On January 25, 2012, Suffolk submitted its first claim to the CO. Complaint ¶ 16;
Answer ¶ 16. The claim sought to recover $3,167,997 for âadditional costs incurred [by
Suffolk] while performing out-of-scope work.â Complaint ¶ 16. The CO issued a final
decision rejecting Suffolkâs claim in full. Id. ¶ 17; Answer ¶ 17. Suffolk appealed the COâs
final decision to the Board, and the appeal was docketed as CBCA 2954 (General Conditions
Claim). Suffolk subsequently reduced the amount it is seeking under the General Conditions
Claim to $2,966,229.
Suffolk submitted a second claim to the CO on April 23, 2012. Complaint ¶ 19;
Answer ¶ 19. This claim requested $1,050,957 for additional costs incurred by Suffolk âon
account of GSAâs directive to perform post-completion remedial and reconstruction workâ
on the building to repair damage caused by a major rainstorm. Complaint ¶ 19. The COâs
final decision denied Suffolkâs claim, and Suffolk appealed the final decision to the Board.
Id. ¶ 20; Answer ¶ 20. The appeal was docketed as CBCA 2955 (Cistern Leak Claim).
CBCA 4377 3
Suffolk subsequently reduced the amount it is seeking under the Cistern Leak Claim to
$1,008,638.
On May 31, 2012, Suffolk submitted a claim to the CO requesting $5,724,126 in
additional compensation for one of Suffolkâs subcontractors, N.B. Kenney Company, Inc.
Complaint ¶ 11; Answer ¶ 11. This claim was denied in full by CO final decision.
Complaint ¶ 12; Answer ¶ 12. Suffolk appealed the COâs final decision to the Board, and
the appeal was docketed as CBCA 2953 (Kenney Claim). Suffolk subsequently submitted
a revised claim to the CO, reducing the amount it was seeking to $5,128,960. Complaint
¶ 13.