CBCA 8363
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: Williams Building Company, Inc.
Date: 2025-11-03
Outcome: dismissed
DISMISSED FOR LACK OF JURISDICTION: November 3, 2025
CBCA 8363
WILLIAMS BUILDING COMPANY, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Douglas L. Patin and Erik M. Coon of Bradley Arant Boult Cummings LLP,
Washington, DC, counsel for Appellant.
Neil S. Deol, Office of General Counsel, Department of Veterans Affairs, Decatur,
GA, counsel for Respondent.
Before Board Judges LESTER, GOODMAN, and SHERIDAN.
LESTER, Board Judge.
Appellant, Williams Building Company (WBC), has requested that the Board allow
it to withdraw this appeal but without prejudice to its ability to raise the challenges that it has
identified in the claim underlying this appeal in another case that is currently pending before
the Board. WBC seeks specific declaratory relief in this appeal that subsequent
circumstances have rendered moot, but it is seeking monetary compensation in the related
appeal for the alleged agency breaches of contract upon which this appeal is based. Because
it is clear that the Board lacks jurisdiction to entertain this appeal, we dismiss it for lack of
jurisdiction, which effectively acts as a dismissal without prejudice.
CBCA 8363 2
Background
On December 9, 2020, the Department of Veterans Affairs (VA) awarded a contract
to WBC for a construction project at the Togus VA Medical Center in Augusta, Maine.
WBC alleges that, soon thereafter, it identified numerous latent defects in the plans for the
project for which it sought answers through the submission of requests for information
(RFIs). It asserts that the VA refused to cooperate with WBC in resolving those design
defects and that, on November 3, 2021, it asked the VA to terminate the contract for
convenience. It further alleges that, on January 4, 2022, the VA suspended work on the
project; that the VA later insisted that WBC submit replacement drawings for the entirety of
the project, which it did under protest; and that, on August 22, 2022, the VA refused to
terminate the contract for convenience. Asserting that the price of the project would increase
dramatically using the new drawings, WBC in March 2023 requested a substantial increase
in the contract price, a request to which WBC says the VA contracting officer never
responded. The parties continued to interact and exchange blame for the next several months
about problems on the project.
In July 2024, WBC submitted a request for an equitable adjustment (REA) seeking
payment of more than $7.7 million for what it called the VA’s breach of the contract. On
September 26, 2024, it converted that REA into a certified claim in accordance with
section 7103 of the Contract Disputes Act (CDA), 41 U.S.C. § 7103 (2018).
In October 2024, at the contracting officer’s direction, WBC remobilized on site.
WBC alleges that it was later told to perform work in accordance with the original design and
not in accord with proposed change orders, which WBC asserted could not be done. The
parties continued to conflict about the work to be performed.
Then, on November 26, 2024, WBC submitted to the VA contracting officer what it
called a “Claim for Declaratory Relief” under the CDA in which it “request[ed] a final
decision/contract interpretation by . . . the Contracting Officer, that the VA has materially
breached the contract, and that [WBC] has the right to stop work.”
On February 26, 2025, WBC filed this appeal, which the Clerk of the Board docketed
as CBCA 8363, from the “deemed denial” of its November 26 declaratory relief claim.
Soon thereafter, on March 20, 2025, WBC filed with the Board a notice of appeal
from the contracting officer’s “deemed denial” of its September 26, 2024, monetary claim,
which the Clerk of the Board docketed as CBCA 8390.
CBCA 8363 3
On July 24, 2025, the VA contracting officer terminated the contract for default.
WBC appealed the termination decision to the Board that same day, which the Clerk of the
Board docketed as CBCA 8519.
By order dated August 25, 2025, the Board requested that WBC show cause as to
whether, in light of the default termination, there was any remaining live dispute in
CBCA 8363, given that the request in that appeal was for permission to allow WBC to stop
work on the contract.