ASBCA 59531
Board: ASBCA
Date: 2016-06-09
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Columbia State Bank ) ASBCA No. 59531
(formerly Appeal of Castle-Rose, Inc.) )
)
Under Contract No. W912DW-10-C-0015 )
APPEARANCE FOR THE APPELLANT: Erich M. Paetsch, Esq.
Saalfeld Griggs PC
Salem, OR
APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.
Engineer Chief Trial Attorney
Ian D. Clunies-Ross, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Seattle
OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN ON APPELLANT'S
MOTION FOR SUMMARY JUDGMENT
This appeal arises from a contracting officer's (CO's) final decision (COFD)
denying the claim of Castle-Rose, Inc. (CRI), for costs of a constructive change, differing
site conditions, government-caused delays, and expert consulting fees incurred on a
contract for construction of new buildings at the Howard Hanson Dam in Cumberland,
Washington. 1 CRI has moved for summary judgment on entitlement as to each claim
item. For the reasons stated below, we deny the motion.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. On 19 May 2010, the U.S. Army Corp of Engineers, Seattle District (Corps or
government) awarded Contract No. W912DW-10-C-0015 (contract) to CRI for the
construction of an administration building and an addition to the existing maintenance
building at the Howard Hanson Dam (HHD) Facility in Cumberland, Washington. The
contract included multiple contract line item numbers (CLINs) for a total firm-fixed-price
of $2,288,900. (R4, tab 3 at 3-4, 92) CRI was required to furnish all labor, materials and
1
CRI subsequently entered into Chapter 7 bankruptcy proceedings, and the Bankruptcy
Court assigned its claim to Columbia State Bank, which entered its appearance as
the real party in interest authorized to pursue the appeal on behalf of the
bankruptcy estate (see SOF ~~ 23-24).
2
Citations to the Rule 4 file are to the consecutively-numbered pages unless otherwise
indicated.
equipment on the project in accordance with the drawings and technical specifications
incorporated into the contract (id. at 3).
2. The contract incorporated the following standard Federal Acquisition
Regulation (FAR) clauses: 52.233-1, DISPUTES (JUL 2002); 52.236-2, DIFFERING SITE
CONDITIONS (APR 1984); 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING
THE WORK (APR 1984); 52.242-14, SUSPENSION OF WORK (APR 1984); and 52.243-4,
CHANGES (JUN 2007) (R4, tab 3 at 24 ).
3. FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) provides, in relevant
part, that:
(a) The Contractor shall promptly, and before the
conditions are disturbed, give a written notice to the
Contracting Officer of ( 1) subsurface or latent physical
conditions at the site which differ materially from those
indicated in this contract, or (2) unknown physical conditions
at the site, of an unusual nature, which differ materially from
those ordinarily encountered and generally recognized as
inhering in work of the character provided for in the contract.
(b) The Contracting Officer shall investigate the site
conditions promptly after receiving the notice. If the
conditions do materially so differ and cause an increase or
decrease in the Contractor's cost of, or the time required for,
performing any part of the work under this contract, whether
or not changed as a result of the conditions, an equitable
adjustment shall be made under this clause and the contract
modified in writing accordingly.
4.