ASBCA 60416
Board: ASBCA
Agency: Navy
Appellant: Sparton DeLeon Springs, LLC
Date: 2016-12-28
Outcome: sustained
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Sparton DeLeon Springs, LLC ) ASBCA No. 60416
)
Under Contract Nos. N00164-0l-D-0027 )
NOO 167-04-D-0024 )
APPEARANCES FOR THE APPELLANT: Nicole J. Owren-Wiest, Esq.
Gary S. Ward, Esq.
Wiley Rein LLP
Washington, DC
APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq.
DCMA Chief Trial Attorney
Gregory T. Allen, Esq.
Trial Attorney
Defense Contract Management Agency
Chantilly, VA
OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
ON APPELLANT'S MOTION FOR JUDGMENT ON THE PLEADINGS, AND
ALTERNATIVELY FOR SUMMARY JUDGMENT
Appellant, Sparton DeLeon Springs, LLC (Sparton), timely appeals from a
26 October 2015 contracting officer's final decision demanding the reimbursement of an
alleged overpayment of certain direct costs. Appellant requests judgment on the pleadings,
or summary judgment that the government's claim is time-barred. The appeal is governed
by the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109.
STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
The following is not in dispute. In 2001, Sparton's predecessor, Sparton Electronics
Florida, Inc. (SEFI), and the government entered into Contract No. N00164-01-D-0027
(Contract 27) for research and development related to sonobuoys (answer at 2, ~ 4). By 2005,
the government had issued Delivery Orders 4, 8, 14, 15, and 16 to Contract 27 (id. at 2-3,
~~ 5-9). In 2004, SEFI and the government entered into Contract No. N00167-04-D-0024
(Contract 24) for engineering and technical services related to repair and maintenance of
submarine acoustics (id. at 3 ~ 10). By 2006, the government had issued Delivery Orders 2
and 3 to Contract 24 (id. at 4, ~~ 11-12).
Contract 27 incorporated by reference Federal Acquisition Regulation (FAR) clause
52.216-7' ALLOWABLE COST AND PAYMENT (MAR 2000); Contract 24 incorporated by reference
the December 2002 version of the same clause (answer at 4,, 13). Both versions provide the
following:
(g) Audit. At any time or times before final payment, the
Contracting Officer may have the Contractor's invoices or
vouchers and statements of cost audited. Any payment may be-
( 1) Reduced by amounts found by the Contracting Officer
not to constitute allowable costs; or
(2) Adjusted for prior overpayments or underpayments.
By 10 January 2007, the government had paid interim vouchers that SEFI had
submitted that included breakdowns of certain intra-company "Jackson Engineering Support
Costs" (Jackson costs) that SEFI allegedly incurred at its Jackson, Michigan plant, and that are
the subject of this appeal (gov't resp. at 4,, 1, at 6,, 6, at 8, ,, 12-13). On 5 March 2007,
Sparton submitted to the government its final indirect cost rate proposal for its fiscal year 2006
(FY 06); on 29 January 2008, Sparton submitted its final indirect cost rate proposal for its
fiscal year 2007 (FY 07) (id. at 8-9,, 14). Both proposals included a "Schedule I," which the
government also calls a "Cumulative Allowable Cost Worksheet-('CACWS')" (id. at 9,, 15,
at 11,, 20, at 14-15,, 27). In neither proposal (more specifically, in neither Schedule I) did
Sparton include the Jackson costs (id. at 9,, 15).
During subsequent Defense Contract Audit Agency (DCAA) audits of the indirect
cost rate proposals, Sparton submitted revisions of those proposals (gov't resp. at 10,, 17).
Sparton submitted the revision of the FY 06 proposal on 25 August 2011, and the revision
of the FY 07 proposal on 30 July 2013 (answer at 4-5, ,, 14-15). The revised proposals did
not include the Jackson costs (gov't resp. at 10, , 17). In September 2013, DCAA issued
audit reports on those indirect cost rate proposals, noting that the proposals did not include
the Jackson costs (answer at 5-6, ,, 16-17).
The parties eventually executed final indirect cost rate agreements for FY 06 and
FY 07, and Sparton provided updated Schedule I forms reflecting the agreed-upon rates
(gov't resp. at 10-11, ,, 19-20). On 2 April 2014, Sparton provided an updated Schedule I
for FY 06; on 23 May 2014, it provided an updated Schedule I for FY 07 (answer at 6,, 19; ·
gov't resp. at 15, , 30).