CBCA 6031-R
Board: CBCA
Agency: Department of Agriculture
Appellant: Woolery Timber Management Inc.
Date: 2019-04-04
Outcome: denied
RECONSIDERATION DENIED: April 4, 2019
CBCA 6031-R
WOOLERY TIMBER MANAGEMENT INC.,
Appellant,
v.
DEPARTMENT OF AGRICULTURE,
Respondent.
Charlotte Woolery, President of Woolery Timber Management Inc., Tuolumne, CA,
appearing for Appellant.
John Eichhorst, Office of the General Counsel, Department of Agriculture, San
Francisco, CA, counsel for Respondent.
LESTER, Board Judge.
On January 31, 2019, the Board issued its decision in this appeal, awarding appellant,
Woolery Timber Management Inc. (WTM), $4008.32 in costs associated with a blocked
access road to the project site, plus interest pursuant to the Contract Disputes Act (CDA), 41
U.S.C. § 7109(a) (2012), but denying the remainder of WTMâs $86,674.04 claim. See
Woolery Timber Management Inc. v. Department of Agriculture, CBCA 6031, 19-1 BCA
¶ 37,245, at 181,293. Respondent, the United States Forest Service (USFS), acting through
the Department of Agriculture, seeks reconsideration of the damages award to WTM, arguing
that the Boardâs findings of fact were incorrect and asking that we award WTM no damages.
In our prior decision, we found âit more likely than not, based upon a preponderance
of the evidence, that WTM had been relying on a service road for access to the portion of the
CBCA 6031-R 2
project area that it was working, that the area was accidentally blocked, and that WTM lost
thirty-two hours of work time having to take an alternative route to that project area.â
Woolery Timber Management, 19-1 BCA at 181,293. We based that finding upon significant
evidence in the record, contemporaneous with the events in question, showing that WTMâs
vice president and project manager, Ed Woolery, was complaining to the USFS about
blocked road access during this period of time. We also indicated that the contracting
officerâs representative (COR) did not actually go to the disputed area to check access during
that time. On reconsideration, the USFS provides a declaration from the COR indicating that
the latter finding is incorrect.
Discussion
This appeal is proceeding under the small claims procedure set forth in Board Rule 52,
48 CFR 6101.52 (2018). Although Rule 52(c) provides that the Boardâs decision in a small
claims procedure case âis final and conclusive [and] shall not be set aside except for fraud,â
nothing in our rules expressly precludes a party from seeking reconsideration of a decision
in such a case, and the Board has routinely entertained reconsideration requests in such cases.
See, e.g., Native American Construction Services, LLC v. Department of the Interior, CBCA
5232-R, 16-1 BCA ¶ 36,542, at 178,021; G2G, LLC v. Department of Commerce, CBCA
4845-R, 15-1 BCA ¶ 36,163, at 176,471; Michael C. Lam v. General Services
Administration, CBCA 1213-R, 09-1 BCA ¶ 34,105, at 168,643. Accordingly, the USFSâs
reconsideration, timely filed under Board Rule 26(b) within thirty days following the USFSâs
receipt of the January 31 decision, is properly before us. Because the case was originally
decided by a single judge under the Boardâs small claims procedure, the same single judge
similarly will decide the reconsideration motion. Michael C. Lam, 09-1 BCA at 168,644.
On the merits of the USFSâs reconsideration request, we generally do not accept new
evidenceâin this case, a post-hearing declaration supplementing the prior hearing testimony
of a fact witnessâthat was or could with due diligence have been reasonably available to the
party during the prior hearing. Meredith Relocation Corp., GSBCA 9124, et al., 90-3 BCA
¶ 23,129, at 116,124. The declaration is submitted to convince us that, contrary to our factual
finding, the COR actually visited the section of the project site where WTM alleges its road
access was blocked and that the COR could find no such road, much less blockage. Most
statements contained in that declaration repeat the CORâs hearing testimony, and anything
new could have been presented at the hearing. Accordingly, the CORâs declaration is not
ânewâ under the standard for accepting evidence on reconsideration.
Even considering the declaration, though, it does not change the result of the blocked
access road issue. We do not doubt the integrity of the COR or his efforts to work with
WTM to obtain proper mastication work under the contract at issue. The contemporaneous
CBCA 6031-R 3
documentary evidence is clear that, back in the spring of 2017, Mr.