CBCA 7587
Board: CBCA
Agency: General Services Administration
Appellant: BES Design/Build, LLC
Date: 2023-04-06
Outcome: dismissed
DISMISSED FOR LACK OF JURISDICTION: April 6, 2023
CBCA 7587
BES DESIGN/BUILD, LLC,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Jerome E. Speegle of Speegle, Hoffman, Holman & Holifield, LLC, Mobile, AL,
counsel for Appellant.
Kelly Y. Burnell and David C. Charin, Office of General Counsel, General Services
Administration, Washington, DC, counsel for Respondent.
Before Board Judges DRUMMOND, KULLBERG, and ZISCHKAU.
DRUMMOND, Board Judge.
Respondent filed a motion to dismiss for lack of jurisdiction, arguing that this claim
is a resubmission of a previous claim that appellant did not timely appeal. For the reasons
below, we grant respondentâs motion and dismiss the appeal for lack of jurisdiction.
Findings of Fact
The General Services Administration (GSA) entered into a general construction,
indefinite-delivery, indefinite-quantity contract (GS-04P-15-EZ-D-0011) with BES
CBCA 7587 2
Design/Build, LLC (BES). Appeal File, Exhibits 1â3.1 Under that contract, GSA awarded
BES a task order (GS-P-04-16-EX-7486) for $348,227 to replace two exterior stairs at a
courthouse in Statesville, North Carolina. Exhibit 6. During performance, disputes arose
relating to issues of performance and non-payment.
On February 24, 2021, BES submitted a certified claim for $37,816.15 to the
contracting officer (CO). Exhibit 16 at 1. According to BES, the contract work had been
completed, and GSA refused to pay the remaining balance. Id.
On April 23, 2021, the CO issued a contracting officerâs final decision (COFD)
denying BESâs claim and including the statement, âThis is the final decision of the
contracting officer.â Exhibit 19 at 1. The COFD also provided notice to BES of its appeal
rights. The COFD was sent electronically to BESâs owner and several other BES
representatives on the day of issuance. Exhibit 18.
Over one year later, on June 8, 2022, BES submitted a claim to the CO that was nearly
identical to the February 24, 2021, claim.2 On August 22, 2022, the CO responded to the
letter, informing BES that a COFD had already been issued on the matter on April 23, 2021.
Exhibit 25. BES makes no contention that it did not receive the April 23, 2021, COFD.
Eighty-eight days later, on November 18, 2022, BES filed a notice of appeal with this
Board, stating that BES was appealing a COFD issued on August 22, 2022, and referencing
the COâs email to BES of that date. In response, GSA filed a motion to dismiss for lack of
jurisdiction.
Discussion
The Contract Disputes Act (CDA), 41 U.S.C. §§ 7101â7109 (2018), governs the
jurisdiction of the Board and authorizes the Board to review a COFD on a contractorâs claim.
Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1573 (Fed. Cir. 1995). There are three components,
or prerequisites, to our ability to hear a contractorâs claim for money under the CDA: the
contractorâs submission of the claim to the CO, the issuance of a COFD or occurrence of a
deemed denial, and a timely appeal. Bass Transportation Services, LLC v. Department of
1
All exhibits are found in the appeal file, unless otherwise noted.
2
The only difference between the claims was that BES lowered its sum certain
because GSA made a payment between the submittals of the first and second claims.
Compare Exhibit 16 (certified claim from February 24, 2021) with Exhibit 24 (certified claim
from June 8, 2022); see Exhibit 21 at 4 (e-mails approving a payment of $6189).
CBCA 7587 3
Veterans Affairs, CBCA 4995, 16-1 BCA ¶ 36,464, at 177,688; see Safe Haven Enterprises,
LLC v. Department of State, CBCA 3871, et al., 15-1 BCA ¶ 35,928, at 175,603.
First, the contractor must have appropriately submitted a valid CDA claim to the CO.
The CDA itself does not define âclaim,â but it has been established that a non-routine
âclaimâ for money be â(1) a written demand, (2) seeking, as a matter of right, (3) the
payment of money in a sum certain.â Reflectone, 60 F.3d at 1575. Here, BESâs February
24, 2021, letter to the CO was a valid claim under the CDA. The claim consisted of a
contractorâs written demand seeking payment as required under the contract with a sum
certain of $37,816.15. The claim also included an explicit request for a COFD and described
the basis for the claim.
Second, an appeal must stem from a COFD or a deemed denial.