CBCA 4011
Board: CBCA
Appellant: Rak Contractors, LLC
Date: 2015-03-19
DENIED: March 19, 2015
CBCA 4011
RAK CONTRACTORS, LLC,
Appellant,
v.
DEPARTMENT OF AGRICULTURE,
Respondent.
Richard A. Kubilus, Sr., President of RAK Contractors, LLC, Wellington, FL,
appearing for Appellant.
Daniel B. Rosenbluth, Office of the General Counsel, Department of Agriculture,
Golden, CO, counsel for Respondent.
Before Board Judges HYATT, VERGILIO, and SULLIVAN.
VERGILIO, Board Judge.
On July 29, 2014, the Board received from RAK Contractors, LLC (contractor) a
notice of appeal contesting the termination for default of its contract, AG-32SD-P-13-0883,
with the Department of Agriculture (agency). The contractor was to have replaced a heating,
ventilation, and air conditioning (HVAC) unit, but did not obtain a unit from the
manufacturer or elsewhere. The contractor lacked sufficient credit to purchase the unit from
the manufacturer and did not obtain money from a bank or otherwise to complete a purchase.
The contractor contends that its failure to perform was for reasons beyond its control and
without its fault or negligence, such that the default should be converted to one for
convenience.
CBCA 4011 2
The agency has moved for summary judgment (treated by the Board as a motion for
summary relief), contending that there is no genuine issue of material fact. It asserts that the
contractor did not complete performance under the contract and that the reasons put forward
by the contractor do not constitute bases to convert the termination to one for convenience.
The contractor opposes the motion, as it contends that its failure to perform arose from
reasons beyond its control. The contractor further notes that the contracting officer failed to
notify it prior to award that its bid was lower than others. The contractor also states that with
an opportunity it may have withdrawn its bid. Also, the contractor contends that the
contracting officer simply should have terminated the contract for convenience. Given the
issues and positions of the parties, further development of the record is unnecessary; as
suggested by the agencyâs motion and the response by the contractor, this matter is ripe for
resolution.
The Board makes findings of uncontroverted fact consistent with the assertions of the
parties and the written record. The Board concludes that the contractor failed to perform,
such that the agency has met its burden of proof. Relying upon facts as asserted by the
contractor, the contractor has not established that its failure to perform arose from reasons
beyond its control. Its lack of financing sufficient to satisfy the manufacturer does not
constitute a reason beyond its control. The contractor has not established a correctable
mistake in its pricing raised post-award: it bid the price intended, although it learned after
award that the contract price was below the purchase price of a new unit from the
manufacturer. Nothing alleged by the contractor suggests that a mistake occurred, other than
of judgment, or that the contracting officer knew or should have known of or suspected a
mistake. Given that the agency had a continuing need for the contract work to be performed,
the contractor has not established that the contracting officer erred by issuing a termination
for default rather than one for convenience. The contractor has not raised a basis that would
excuse the default. Accordingly, the Board grants the motion for summary relief and denies
the appeal.
Findings of Fact
1. Under simplified acquisition procedures, the agency issued a solicitation to
obtain bids for a contractor to replace a rooftop HVAC unit. The solicitation sought a single
line item bid price to perform all of the required work, including the delivery of the unit and
installation. The solicitation stated that payment security is required if the contract award is
for $30,000 or more. Exhibit 2 at 3-4, 8 (all exhibits are in the appeal file). Seven
companies responded, with unit prices ranging from the two lowest of $24,661 and $30,645,
to the two highest of $61,600 and $62,500. Exhibit 3 at 25-27.
CBCA 4011 3
2. On September 28, 2013, the agency and contractor entered into a contract that
required the contractor to provide and install a particular make and model HVAC
replacement unit within sixty calendar days after receipt of the notice to proceed. The
contract price was $24,661. Exhibits 2 at 4-5, 4 at 3 (¶ 10), 31-32, 36, 95, 104-11.
3.