ASBCA 62732
Board: ASBCA
Agency: Army
Appellant: Zahra Rose Construction
Date: 2022-04-13
Outcome: sustained
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Zahra Rose Construction ) ASBCA No. 62732
)
Under Contract No. W91B4N-20-P-0015 )
APPEARANCE FOR THE APPELLANT: Ms. Zahra Noori
CEO
APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq.
Army Chief Trial Attorney
LTC Abraham Young, JA
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE SMITH
In this appeal, we resolve appellant Zahra Rose Constructionâs (Zahra)
challenge to respondent Armyâs (the government) final decision regarding the
termination for convenience after approximately two weeks of Zahraâs two-month
$30,000 contract to lease fuel trucks in Afghanistan. The contracting officerâs final
decision provided a $15,000 termination settlement under Federal Acquisition
Regulation (FAR) 52.212-4(l) while Zahra claims that it is entitled to $30,400 because
Zahra paid the owner of the trucks in advance for the full contract term in order to
obtain the trucks. In response, the government disavows its $15,000 settlement
decision and argues that Zahra is entitled to no settlement because the trucks did not
meet the contractâs technical requirements. Alternatively, the government argues that
if Zahra is entitled to any termination settlement, it should be no more than $6,300
based upon a 12-day pro-rata calculation. For the reasons discussed below, we find
that Zahra is entitled to a termination settlement of $28,800, which Zahra has
sufficiently demonstrated it reasonably incurred prior to termination. We sustain the
appeal in the amount of $28,800, but deny the appeal for the remainder of Zahraâs
claim.
FINDINGS OF FACT
After a brief negotiation by email between September 2 and September 4, 2020
(app. supp. R4, tab 1 at 35, 40; tab 10; tab 16; tabs 27-29), Zahraâs sole-source
Contract No. W91B4N-20-P-0015 (the contract) was executed on September 4 by
Zahra and on September 7 by the government (app. supp. R4, tab 2 at 52; R4, tab 2
at 1). 1 The contract was 16-pages, commensurate with the cost and scope of a $30,000
lease of two fuel trucks (R4, tab 2 at 1, 3). The contract quantity was â2â and the units
were âmonths.â (Id. at 3) The period of performance was also described as â04-SEP-
2020 TO 31-OCT-2020â (id.) and â03 September 2020 to 31 October 2020â (R4, tab 2
at 14). The pre-award price discussions were based on cost per truck per month (app.
supp. R4, tabs 10, 27, 29).
In general, the contract required delivery of two 10,000-liter fuel trucks to
Camp Antonik, Helmand Province, Afghanistan for use by the government (R4, tab 2
at 14-15; tab 19 at 9). Zahra was responsible for maintenance or repair of the trucks as
needed, and retrieval of the trucks at the conclusion of the contract (id. at 3, 15-16).
The contract contained a list of approximately 24 technical requirements for the
trucks, some related to fuel delivery functions (fuel pump capacity, specific nozzles,
etc.), while others were safety items (seat belts, rear view mirror, etc.) (id. at 15).
The contract was a commercial items procurement, and incorporated the 2018
version of FAR 52.212-4 âContract Terms and Conditions--Commercial Itemsâ (id.
at 4; see also id. at 1).
FAR 52.212-4(a), INSPECTION/ACCEPTANCE, provided:
âThe Contractor shall only tender for acceptance those
items that conform to the requirements of this contract.
The Government reserves the right to inspect or test any
supplies or services that have been tendered for
acceptance. The Government may require repair or
replacement of nonconforming supplies or reperformance
of nonconforming services at no increase in contract price.
. . . The Government must exercise its post-acceptance
rights . . . within a reasonable time after the defect was
discovered or should have been discovered . . . .â
FAR 52.212-4(a) (emphasis added).
The contractâs termination provision was FAR 52.212-4(l) and provided:
âThe Government reserves the right to terminate this
contract, or any part hereof, for its sole convenience . . .