CBCA 7549
Board: CBCA
Agency: Department of State
Appellant: Framaco International Inc.
Date: 2024-07-29
Outcome: granted
THIS OPINION WAS INITIALLY ISSUED UNDER PROTECTIVE ORDER AND
IS BEING PUBLICLY RELEASED IN ITS ENTIRETY ON JULY 31, 2024
GRANTED: July 29, 2024
CBCA 7549
FRAMACO INTERNATIONAL INC.,
Appellant,
v.
DEPARTMENT OF STATE,
Respondent.
Douglas L. Patin, Erik M. Coon, and Jennifer M. Ersin of Bradley Arant Boult
Cummings LLP, Washington, DC; and Sam Z. Gdanski and Abraham S. Gdanski of Gdanski
Law PC, Teaneck, NJ, counsel for Appellant.
Thomas D. Dinackus, Matthew S. Tilghman, and Alexandra N. Wilson, Office of the
Legal Adviser, Buildings and Acquisitions, Department of State, Washington, DC, counsel
for Respondent.
Before Board Judges BEARDSLEY (Chair), RUSSELL, and O’ROURKE.
RUSSELL, Board Judge.
Appellant, Framaco International Inc. (Framaco), has filed 131 cases with the Board
(certain of which are consolidated) based on its contract with respondent, Department of
State (State or agency), Bureau of Overseas Building Operations (OBO), to construct an
embassy compound in Port Moresby, Papua New Guinea.
CBCA 7549 2
This decision is being issued in accordance with the Board’s order on further
proceedings of October 19, 2023 (Order), which largely adopted the parties’ proposal to
resolve approximately 100 of appellant’s non-consolidated appeals brought pursuant to
Board Rule 53 (48 CFR 6101.53 (2023)), along with certain claims in four of its consolidated
appeals that were not based on Government-caused delay. See Rule 53 (governing
accelerated procedures, which are available at an appellant’s election and are limited to
appeals in which there is a monetary amount in dispute of $100,000 or less); see also
Rule 1(a) (“The Board may alter [its] procedures on its own initiative or on request of a party
to promote the just, informal, expeditious, and inexpensive resolution of a case.”). The Order
states that “[t]he presiding judge with the two members of the panel . . . will decide the
following appeals for which the parties will submit briefing: CBCA 7508, 7512, 7513, 7549,
7561, 7572, 7573, 7625, 7695, 7712, 7847, and 7859 (‘Selected Appeals’).” The Order
additionally states, “Decisions rendered by the panel will be in summary form either in
writing or orally, if a hearing is held; will be final and conclusive; will not be set aside,
except for fraud; and will not be precedential.”
As agreed to by the parties, quantum in the non-consolidated appeals and certain
claims in four of Framaco’s consolidated appeals to which the Order applies will be decided
based on a formula derived from any damage amounts awarded to Framaco in the Selected
Appeals. In a subsequent joint response filed with the Board on March 19, 2024, the parties
confirmed that the Order applies to the appeals described above.
In this appeal, Framaco seeks $81,452 for the cost of purchasing and installing an
X-ray machine that Framaco claims was not required by the contract. Exhibit 23 at DOS-
PTMO-03088660. Alternatively, Framaco asserts that, if the machine were required, it
should have been furnished by State. Id. State asserts that the contract unambiguously
required Framaco to provide the X-ray machine. Respondent’s Initial Brief at 1. For reasons
stated below, we grant the appeal.
Background
I. The Contract
In September 2015, State awarded Framaco a firm-fixed-price contract, initially
valued at approximately $97 million to construct the New Embassy Compound (NEC) in
CBCA 7549 3
Port Moresby, Papua New Guinea.1 Appeal File, Exhibit 1 at DOS-PTMO-00982321.2 The
project was originally designed in 2010 as a “Standard Secure mini-Compound” (SSmC)
with a scope including a lock-and-leave new office building, a perimeter security wall and
fence, a main compound entry pavilion (MCAP), a service entry/utility building, and a
support annex. Exhibit 2 at DOS-PTMO-00982414. Construction of the SSmC facility
began in 2012, but in 2013, after forty percent of the project was completed, a future marine
detachment was planned for Port Moresby and the embassy staffing requirement was
increased. Id. State therefore descoped the work under the 2012 contract and closed out that
contract. The project was redesigned under an expanded NEC, incorporating the completed
portions of the SSmC project as well as surplus equipment and materials, where appropriate.
Id.