ASBCA 62779
Board: ASBCA
Agency: Army Corps of Engineers
Appellant: RLB Contracting, Inc.
Date: 2023-06-15
Outcome: dismissed
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
RLB Contracting, Inc. ) ASBCA No. 62779
)
Under Contract No. W9126G-17-C-0043 )
APPEARANCES FOR THE APPELLANT: Michael H. Payne, Esq.
Casey J. McKinnon, Esq.
Cohen Seglias Pallas Greenhall
& Furman, P.C.
Philadelphia, PA
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Clark Bartee, Esq.
Engineer Trial Attorney
U.S. Army Corps of Engineers District,
Galveston
OPINION BY ADMINISTRATIVE JUDGE SWEET
This appeal involves dredging work that appellant RLB Contracting, Inc. (RLB)
performed for the United States Army Corps of Engineers (Corps or USACE) in the
Gulf Intracostal Waterway (GIWW), Texas Main Channel, San Antonio Bay, Texas.
While performing that work, RLB struck the Tomcat West Pipeline (Pipeline)âa
submerged natural gas pipelineâcausing an explosion that damaged the dredger, and
allegedly delayed completion of the contract. The Corps imposed liquidated damages.
RLB submitted a claim to the contracting officer (CO) seeking a time extension and
remission of the liquidated damages due to the purported excusable delays of defective
specifications, differing site conditions, and a breach of the duty of good faith and fair
dealing. After the CO denied that claim, RLB filed this appeal. The Corps moves for
summary judgment on all of RLBâs causes of action. We grant that motion and
dismiss this appeal for the reasons discussed below.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
I. The Pipeline
1. The Pipeline was a natural gas pipeline owned by Genesis Energy (Genesis)
that crossed the GIWW (R4, tabs 1 at 39, 10 at 277, 282-83).
2. In a November 2016 email chain (Email Chain), Corps personnel expressed
concerns that the Pipeline and another pipeline were not adequately buried to -24 feet
MLWW, 1 and thus at risk of an accidental strike (app. resp. ex. 1 at 814-16).
3. As a result, on November 23, 2016, the Corps forwarded its concerns to
Morris P. Herbert, Inc. (Herbert)âan engineering firm (app. resp. ex. 1 at 812-13;
SAGIMF ¶ 31; RSAGIMF ¶ 31). 2 Herbert forwarded the Corpsâ concerns to Genesis
on November 23, 2016, with an email stating that the Corps was directing Genesis to
lower the pipelines as soon as possible (id. at 812).
4. On November 29, 2016, Herbert wrote to the Corps that â[t]he pipeline will
be lowered to minimum 24 feet MLLW as directed by USACE.â (app. resp. ex. 1
at 809).
5. On March 23, 2017, Herbert sent the Corps an as-built drawing (Genesis As-
Built Drawing) and stated that â[a]s shown on the drawing, the pipeline was lowered
as directed by USACE Operationsâ (app. resp. ex. 6 at 917). The Genesis As-Built
1
âMLLWâ stands for Mean Lower Low Water and means the âaverage of the lower
low water height of each tidal day observed over the National Tidal Datum
Epoch.â See
https://tidesandcurrents.noaa.gov/datum_options.html#:~:text=MLLW*,the%
20National%20Tidal%20Datum%20Epoch.
2
âSUMFâ refers to the Corpsâ statement of undisputed material fact. âRSUMFâ refers
to RLBâs response to the SUMF. âSAGIMFâ refers to RLBâs statement of
additional genuine issues of material fact. âRSAGIMFâ refers to the Corpsâ
response to the SAGIMF.
2
Drawing indicated as follows:
(govât reply ex. 2 at 919). As the Genesis As-Built Drawingâs bottom drawing shows,
the Pipeline was adequately buried to at least -24 feet MLWW for all of the 325-foot
distance between the setbacks (id.). 3 That 325-foot distance was wider than the 300-
foot dredging area in this appeal (R4, tab 1 at 38-39).
II. The 0043 Contract
6. On April 7, 2017, the Corps issued Solicitation W9126G-17-B-0011, which
resulted in the award of Contract No. W9126G-17-C-0043 (0043 Contract) to RLB on
3
RLBâs suggestion that the Genesis As-Built Drawing showed that Genesis only
lowered the Pipeline across the 125-foot channel is incorrect (app. resp.