ASBCA 58871
Board: ASBCA
Date: 2015-09-14
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Environmental Chemical Corporation ) ASBCA No. 58871
)
Under Contract No. FA8903-06-D-8511 )
APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq.
Amy M. Kirby, Esq.
Justin J. Williams, Esq.
Cohen Seglias Pallas
Greenhall & Furman PC
Philadelphia, PA
Kevin J. Kelly, Esq.
Corporate Counsel
APPEARANCES FOR THE GOVERNMENT: Lt Col Matthew J. Mulbarger, USAF
Air Force Chief Trial Attorney
Anna F. Kurtz, Esq.
Capt Christopher M. Kovach, USAF
Trial Attorneys
OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON APPELLANT'S
MOTION TO AMEND COMPLAINT
INTRODUCTION
Appellant moves to amend its complaint to add two counts: one alleging
unabsorbed overhead resulting from delay to the contract work, and one alleging
breaches of the implied duty of good faith and fair dealing. We grant the motion in
part, and deny the motion in part.
STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
In April 2006, Air Force Materiel Command (Air Force) awarded Contract
No. F8903-06-D-8511, an indefinite delivery, indefinite quantity Heavy Engineering
and Repair (HERC) contract, to Environmental Chemical Corporation (ECC) (R4,
tab 9 at 1-2). On 2 September 2011, the Air Force awarded Task Order 81 to the
contract to ECC, for the design and construction of buildings and parking lots at
Kandahar Air Field (KAF), in Afghanistan, for the fixed price of $22,974,828 (R4,
tab 21at1-2). Task Order 81 required the construction of several buildings on KAF
by 2 September 2012 (id. at 3). On 23 August 2012, the Air Force unilaterally issued
Modification No. 3 to Task Order 81, combining some of the buildings, reducing the
size of other buildings, and making other changes to the work (R4, tab 24 at 1, 39-40).
Modification No. 3 also increased the contract price by $1,526,345, and extended the
construction completion date by 129 days, to 9 January 2013 (id. at 2-3).
On 24 January 2013, ECC presented to the contracting officer a claim for
$4,363,296, for subcontractor costs associated with Modification No. 3, and for costs
incurred during a 174-day period of alleged delay that ECC asserted was caused by the
late issuance of Modification No. 3 from 2 March 2012 through 24 August 2012 (R4,
tab 81 at 1-2, 13). 1 The claim references "substantial Govt.-initiated changes to the
project design which were introduced soon after award of the Task Order on
September 2, 2011" (id. at 1). The claim also references specific "design delays,"
including ( 1) a proposal during a 19 September 2011 "initial design charrette" to
combine several buildings into one complex; 2 (2) the issuance by the Air Force on
21September2011 of a new statement of requirements (SOR) for Task Order 81; (3) a
delay through 31 October 2011 of the submittal of the 3 5% design due to the new
SOR; (4) the approval by the Air Force of the 35% design on 4 November 2011;
(5) the issuance by the Air Force of further revisions to the SOR on 19 January 2012,
and 23 February 2012; and (6) the issuance of Modification No. 3 and a notice to
proceed (NTP) with that modification in August 2012 (id. at 11-13). On 8 March
2013, ECC resubmitted its claim, reducing the claim amount to $4,274,135, and
certifying that amount (R4, tab 84 at 3-4). On 28 March 2013, ECC submitted the
claim for a third time, increasing the claim amount to $4,282,762 (R4, tab 89 at 8-9).
On 25 April 2013, ECC certified the 28 March 2013 claim amount (R4, tab 92 at 6).
From 2 April 2013 through 16 October 2013, two Air Force program managers
provided the contracting officer a series of advice memoranda regarding the claim (R4,
tabs 90, 96, 99, 100); the final memorandum recommended that an award to ECC of
303 days (the 129 days awarded in Modification No. 3 plus the 174 days identified in
the claim) was appropriate (R4, tab 100 at 6). On 11 September 2013, ECC filed this
appeal from the deemed denial of its claim. On 15 October 2013, ECC filed its
complaint, requesting $4,282,762 and a time extension of 181 days. On 6 November
2013, the contracting officer issued a final decision awarding to ECC the $1,526,345
amount set forth in Modification No.