ASBCA 58875
Board: ASBCA
Agency: Army Corps of Engineers
Appellant: ECC International, LLC
Date: 2020-08-25
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
ECC International, LLC ) ASBCA No. 58875
)
Under Contract No. W917PM-07-D-0015-0006 )
APPEARANCE FOR THE APPELLANT: Michael A. Richard, Esq.
Obermayer Rebmann Maxwell
& Hippel LLP
Philadelphia, PA
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Sarah L. Hinkle, Esq.
Geoffrey A. Mueller, Esq.
Matthew Tilghman, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Middle East
Winchester, VA
OPINION BY ADMINISTRATIVE JUDGE STINSON
Appellant, ECC International, LLC (ECCI), appeals a contracting officerâs
(CO) deemed denial of its June 6, 2013, certified claim in the amount of $925,216.00
(R4, tab 2). The parties agreed to submit this appeal for a decision on the record
without a hearing pursuant to Board Rule 11. Each party submitted initial and reply
briefs. Also pending are the partiesâ cross-motions for summary judgment, as well as
respondentâs motion to dismiss for lack of jurisdiction. For the reasons stated below,
we deny the governmentâs motion to dismiss, dismiss the partiesâ cross-motions for
summary judgment as moot, and deny the appeal.
FINDINGS OF FACT
The MATOC Contract
1. On August 15, 2007, the Government awarded ECCI Multiple Award Task
Order Contract (MATOC) No. W917PM-07-D-0015, an Indefinite-Delivery,
Indefinite-Quantity contract, âfor general construction and construction related
requirements such as repairs, and/or new construction, including the execution of
design-build construction work throughout Afghanistan.â The contract anticipated
award of task orders in the range of $5 million to $25 million. (R4, tab 3 at 142)
2. Paragraph 1.1 of the MATOC Scope of Work states, in part, that â[t]he vast
majority of these projects will be new construction of relatively simple, one-and
two-story living and working facilities similar to other ânormalâ construction in
Afghanistan, designed to be simple, durable, and easy/inexpensive to maintainâ (R4,
tab 3 at 147).
3. MATOC Scope of Work paragraph 1.4 states, in part:
Where design-build services are required, the contractor
shall employ the services of architect/engineering
professional established in coordination with
multi-discipline architectural/engineering design efforts.
The Contractorâs architect/engineering team shall be
responsible for the coordination of all these disciplines in
the performance of task order work.
(R4, tab 3 at 147)
4. Section 01335 of the MATOC is entitled âSUBMITTAL PROCEDURES
FOR DESIGN-BUILD PROJECTSâ (R4, tab 3 at 186). Paragraph 1.2.1, âDESIGN
SUBMITTALS,â states, in part:
Contractor Furnished design submittals are the various
design documents which primarily consist of
specifications, drawings and design analysis and
calculations. The Design-Build Contractor shall not begin
construction work until the Government has reviewed the
Design-Build Contractorâs final design and has cleared it
for construction. Clearance for construction shall not be
construed as meaning Government approval.