ASBCA 59074
Board: ASBCA
Date: 2014-01-28
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of-- )
)
Dyno Group, Inc. ) ASBCA No. 59074
)
Under Contract No. W912P4-11-C-0016 )
APPEARANCE FOR THE APPELLANT: Edward Everett Vaill, Esq.
Malibu, CA
APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.
Engineer Chief Trial Attorney
Lauren M. Turner, Esq.
Assistant District Counsel
U.S. Army Engineer District, Buffalo
OPINION BY ADMINISTRATIVE JUDGE MELNICK
The United States Corps of Engineers withheld liquidated damages due to the late
completion of a contract by Dyno Group, Inc. (Dyno). Dyno challenged that assessment
in a claim submitted to the contracting officer, which was denied. Dyno has now
appealed and elected to proceed under the Board's Expedited Procedure (Rule 12.2). 1
The appeal is denied.
FINDINGS OF FACT
1. On 22 September 2011, the United States Army Corps of Engineers awarded
Contract No. W912P4-11-C-0016 to Dyno (R4, tab 5). The contract was for the removal
and replacement of staircases inside the Mount Morris Dam in Mount Morris, New York.
The Scope of Work contained a base bid item that required the removal and replacement
of two sections of the south gallery staircase, and five additional optional items,
designated A through E, for the removal and replacement of additional staircases and the
replacement of stair landings. (!d. at 279) The contract was signed for Dyno by
Christopher Wan, its president (id. at 257).
2. Part 1.3 of the section of the contract addressing procedures required Dyno to
"complete the entire work ready for use not later than one-hundred eighty ( 180) calendar
1
The Contract Disputes Act, 41 U.S.C. §§ 7101-7109, implemented by Board Rule
12.2, provides that this decision will have no value as precedent, and in the
absence of fraud shall be final and conclusive and may not be appealed or set
aside.
days from the date of receipt by the Contractor of the Notice to Proceed." It added that
"[ t]or each Option awarded, the Contractor will be given an additional one hundred fifty
(150) days to complete that option." It noted that "[o]ptions may be awarded at any
time within one year of original contract award and options may be awarded
concurrently." (R4, tab 5 at 324)
3. The contract contained 13 contract line item numbers (CLINs). CLINs 1
through 3 were for the base work. The initial award also exercised Options C through E,
reflected in CLINs 8 through 13. (R4, tab 5 at 259-64) The scheduled period of
performance for CLINs 1 through 3 was 180 days, and for CLINs 8 through 13 it was 329
days (id. at 265-66). 2 The contract contained the FAR 52.211-12, LIQUIDATED
DAMAGES-CONSTRUCTION (SEP 2000) clause. In the event Dyno failed to complete the
work within the time specified in the contract, that clause required Dyno to pay $450 in
liquidated damages to the government for each calendar day of delay until the work was
completed or accepted. (!d. at 275) The contract also incorporated the FAR 52.236-2,
DIFFERING SITE CONDITIONS (APR 1984) clause, and the FAR 52.236-3, SITE
INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984) clause (id. at 268).
4. On 30 September 2011, after the contract was awarded, Mr. Wan sent an email
to Brian Steils, the contracting officer representative (COR) (R4, tab 9; compl., tab 17,
,-r 4 ). The email asked whether "the completion timeframe for this job [was] 180 calendar
days?" It noted the "[a]ward amount consists of Base bid and Options C, D, and E" and
asked "do these options give more time for completion (ie does Dyno have 150 days x 3
= 450 additional days), or is it still180 days?" (R4, tab 9) Mr. Steils's 3 October 2011
response referred Mr. Wan to an email from Mr. Walter Kamad from "Contracting."
Mr. Kamad had advised the following:
Just looked over the specs, base bid is 180 days. Since
options C, D and E are awarded with base bid, the breakdown
would be 180 for base bid and an additional 150 days for the
options. The NTP would read 180 days for base bid and to
complete all options in 330 days[.]
(R4, tab 10) Mr. Steils commented that "[t]he contract states 330 days, however USACE
would expect Dyno group to complete the project as soon as possible" (id.).