ASBCA 60484
Board: ASBCA
Agency: United States Army Corps of Engineers
Appellant: ECC International, LLC
Date: 2018-11-16
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
ECC International, LLC ) ASBCA No. 60484
)
Under Contract No. W5J9LE-11-C-0045 )
APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq.
Michael A. Richard, Esq.
Cohen Seglias Pallas Greenhall & Furman PC
Philadelphia, PA
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Sarah L. Hinkle, Esq.
Matthew S. Tilghman, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Middle East
Winchester, VA
OPINION BY ADMINISTRATIVE JUDGE WOODROW
ON THE PARTIES' CROSS-MOTIONS FOR SUMMARY JUDGMENT
Pending before the Board are the parties' cross-motions for summary judgment
filed by appellant, ECC International, LLC (ECCI), and the United States Army Corps of
Engineers (USACE or government). ECCI seeks summary judgment on entitlement to its
monetary claim for costs arising out of the government's closure of the Friendship Gate,
an access route to ECCI's construction site on Camp Shorab in Afghanistan. The
government moves for summary judgment on the grounds that the government's closure
of Friendship Gate was a sovereign act and ECCI assumed the risk of any changes to base
access procedures or requirements.
We hold that the plain language of the contract states that the contractor bears the
risk of changes to base access requirements and that the closure of Friendship Gate was
not a constructive change to the terms of the contract. We further hold that the
government did not create an implied warranty of access through Friendship Gate, and
that ECCI's previous contracts at Camp Shorab in Afghanistan did not create an implied
warranty of continued access to the project site through Friendship Gate.
We do not reach the government's affirmative defense that the closure of the
Friendship Gate was a sovereign act, because we have concluded that there is no express
or implied contractual right of access through the Friendship Gate and that the closure of
Friendship Gate was not a constructive change.
Therefore, we grant the government's motion for summary judgment and deny the
appeal.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
A. The Contract
1. On June 29, 2011, USACE issued Solicitation No. W5J9LE-l l-B-0004
(solicitation) requesting proposals from prospective bidders for the site adapt, design and
construction of the 215th compound expansion, Camp Shorab, Helmand Province,
Afghanistan (R4, tab 3 at 1).
2. The solicitation contained the following provision relating to compliance with
orders relating to force protection: ·
C3 CLAUSE 952.225-0002 ARMED PERSONNEL
INCIDENT REPORTS (SEP 2010)
(a) All contractors and subcontractors in the United States
Forces-Iraq (USF-I) or United States Forces-Afghanistan
(USFOR-A) theater of operations shall comply with and shall
ensure that their personnel supporting USF-I or USFOR-A
forces are familiar with and comply with all applicable
orders, directives, and instructions issued by the respective
USF-I or USFOR-A Commanders relating to force protection
and safety.
(R4, tab 3 at 50)
3. Section 01040 of the solicitation contained the following provision relating to
security in a wartime contingency environment:
1.0 SPECIFIC CONTRACT SECURITY ASSESSMENT
The Contractor will construct the Project in an active war
zone where International Security Assistance Forces (ISAF)
may conduct offensive and defensive operations against a
variety of hostile forces, to include members of the Taliban.
The Contractor understands that it may not receive any
2
support whatsoever in securing the Project site and in
securing the transportation of materials to the Project site.
(R4, tab 3 at 170)
4. Section O1040 of the solicitation further stated that the contractor is responsible
for its own security and securing the transportation of materials to the project site.
"Neither U.S.