CBCA 3258
Board: CBCA
Appellant: Columbia Construction Company
Date: 2015-01-20
GRANTED: January 20, 2015
CBCA 3258
COLUMBIA CONSTRUCTION COMPANY,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Reginald M. Jones and Alexa A. Santora of Fox Rothschild LLP, Washington, DC,
counsel for Appellant.
James F. H. Scott and Claire OâDonnell, Office of the General Counsel, General
Services Administration, Washington, DC, counsel for Respondent.
Before Board Judges STERN, POLLACK, and SHERIDAN.
SHERIDAN, Board Judge.
This is a claim brought by Columbia Construction Company (Columbia) on behalf of
itself and its subcontractor, Wayne J. Griffin Electric, Inc. (Griffin). Columbia was
contracted by the General Services Administration (GSA) to modernize the Internal Revenue
Service (IRS) service center in Andover, Massachusetts. Among other things, the contract
specified that Columbia was to provide a security system, and that the security cabling was
CBCA 3258 2
required to be âconcealed or in conduit (EMT).â1 Columbia seeks an equitable adjustment
of $491,450 for what it characterizes as a GSA-directed change that it asserts occurred when
GSA required it to install the security wiring in EMT conduit, instead of allowing its planned
method of installation in cable trays under the raised access flooring system and above the
drop ceilings. After considering the evidence, including testimony presented at the hearing,
and the partiesâ pre- and post-trial briefs, we find that appellant reasonably interpreted the
contract to allow installation of the security cabling below the raised access floor and above
the ceilings because that installation âconcealedâ the cables as required by the contract.2
Background
On May 6, 2009, GSA issued solicitation GS-01P-09-BZ-C-0014, seeking a contractor
to provide all supervision, labor, materials, and equipment necessary to modernize the IRS
service center. Columbia was awarded the contract on July 21, 2009. Deborah Fournier was
the GSA contracting officer (CO) assigned to administer the contract. The IRS service center
project included upgrades to the buildingâs superstructure, exterior glazing and doors,
heating, ventilation, electrical, fire alarms, and security systems. The design for the
renovated facility also called for installation of a raised access flooring system over the
original concrete pad in approximately eighty percent of the facility. The distance between
the access floor and the original concrete floor varied, from eight inches to two-and-a-half
feet, depending on the conditions encountered. The design for the building incorporated a
security scheme that integrated a variety of security devices including, but not limited to,
glass break detectors, closed circuit televisions, card readers, electronic door locks, panic
buttons, and intercoms. Pre-renovation, the security system cabling was âopen,â and not run
in conduit or raceways.
The project was to be completed in two phases to accommodate partial occupancy of
the service center by the IRS during construction. Prior to entering into the contract, Griffin
submitted a bid to Columbia for the division 26 (electrical), 27 (communications), and 28
(security) contract work. Columbia entered into a subcontract with Griffin for that work on
October 20, 2009. As part of its work, Griffin was required to furnish and install cabling and
devices for the security system at the service center in accordance with the contract.
1
EMT (electrical metallic tubing) is a type of metal tubing used as conduit in
commercial and industrial buildings that is thin enough to be bent.
2
Per its order requiring that all documents, unless mutually agreed upon, be
submitted prior to the hearing, the Board did not accept into the record or consider the
affidavits and documents that were attached to the partiesâ post-hearing briefs.
CBCA 3258 3
The security system work is primarily detailed in the specifications at section 281000,
âSecurity Systems.â Part 1 contains the âGeneral Provisionsâ related to the security systems.
Subpart 1.02.C, titled âProtection Scheme,â provides: âSecurity systems and equipment for
this project shall include, but are not limited to the following . . . 12.