ASBCA 61155
Board: ASBCA
Agency: Army
Appellant: Abdul Khabir Construction Co.
Date: 2018-01-09
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Abdul Khabir Construction Co. ) ASBCA No. 61155
)
Under Contract No. W91B4M-09-C-4063 )
APPEARANCE FOR THE APPELLANT: Mr. Jawad
Corporate Officer
APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.
Army Chief Trial Attorney
MAJ Jason W. Allen, JA
MAJ Bruce L. Mayeaux, JA
Trial Attorneys
OPINION BY ADMINISTRATIVE JUDGE YOUNGER
ON THE GOVERNMENT'S MOTION FOR-SUMMARY JUDGMENT
In this appeal regarding a construction contract terminated for convenience,
the government has moved for summary judgment, contending that appellant failed
to submit its termination settlement proposal within a year of the effective date of
termination, and did not submit its certified claim until more than seven years after
termination. Appellant counters that the government never asked for a settlement
proposal, and never told it where to file a claim. We grant the motion and deny the
appeal.
STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
1. By date of 4 April 2009, the Kabul Regional Contracting Center
(government) awarded Contract No. W91 B4M-09-C-4063 (the contract) to Abdul
Khabir Construction Co. (Abdul Khabir or appellant) for the construction of living
quarters, office buildings, and support facilities at Forward Operating Base (FOB)
Baylough, in Zabul Province, Afghanistan (R4, tab 2 at 2, tab 5 at 5-6).
2. The contract contained two fixed-price contract line item numbers (CLINs).
The first was for construction work at FOB Baylough in the amount of $638,923.68.
(R4, tab 2 at 3-4) The second was for Defense Base Act (DBA) insurance in the amount
of $6,594 (id. at 4, 20-21).
3. The contract incorporated by reference various standard clauses, including
FAR 52.233-1, DISPUTES (JUL 2002); and FAR 52.249-2, TERMINATION FOR
CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (MAY 2004) - ALTERNA TE I (R4,
tab 2 at 22). The latter clause provided, in paragraphs (e) and U):
(e) After termination, the Contractor shall submit a
final termination settlement proposal to the Contracting
Officer in the form and with the certification prescribed by
the Contracting Officer. The Contractor shall submit the
proposal promptly, but no later than 1 year from the
effective date of termination, unless extended in writing by
the Contracting Officer upon written request of the
Contractor within this I-year period. However, if the
Contracting Officer determines that the facts justify it, a
termination settlement proposal may be received and acted
on after 1 year or any extension. If the Contractor fails to
submit the proposal within the time allowed, the
Contracting Officer may determine, on the basis of
information available, the amount, if any, due the
Contractor because of the termination and shall pay the
amount determined.
U) The Contractor shall have the right of appeal,
under the Disputes clause, from any determination made
by the Contracting Officer under paragraph (e) ... ofthis
clause, except that if the Contractor failed to submit the
termination settlement proposal or request for equitable
adjustment within the time provided in paragraph (e ) ... ,
and failed to request a time extension, there is no right of
appeal.
4. By date of 17 July 2009, the contracting officer issued a notice to proceed,
effective the next day (R4, tab 9). Abdul Khabir appears to have received the notice to
proceed on 22 July 2009 (id.). In the notice, the contracting officer directed Abdul
Khabir to "complete all requirements of this project within 120 calendar days of the
effective date of this Notice to Proceed, but no later than 14 November 2009" (id.)
(emphasis in original).
5. The record reflects that Abdul Khabir did not perform any work on the
contract (R4, tabs 10-11 ).
2
6. By email dated 14 January 2010, the contracting officer proposed a no-cost
convenience termination to Abdul Khabir (R4, tab 10).