Nomura Enterprise, Inc.--Request for
Case: B-260977.2
Agency:
Protester: Nomura Enterprise, Inc.
Date: 1995-11-02
Denied
Nomura Enterprise, Inc.--Request for
BNUMBER: B-260977.2; B-260977.3
DATE: November 2, 1995
TITLE: Nomura Enterprise, Inc.--Request for
Reconsideration and Protest
**********************************************************************
Matter of:Nomura Enterprise, Inc.--Request for
Reconsideration and Protest
File: B-260977.2; B-260977.3
Date: November 2, 1995
John W. Reimers and Al Weed, Esq., for the protester.
Caridad Ramos, Esq., and Jeffrey I. Kessler, Esq., Department of the
Army, for the agency.
Laurence Schor, Esq., Smith, Somerville & Case, for Barnes & Reinecke,
Inc., an interested party.
M. Penny Ahearn, Esq., and David A. Ashen, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest against award of sole source contract for engineering support
services related to the M109 self-propelled howitzer is denied where
agency reasonably concluded that unacceptable delays would occur if
award were made to another source prior to completion of current
production due to massive amount of materials and equipment which
would have to be transferred to new contractor.
DECISION
Nomura Enterprise, Inc. (1) requests reconsideration of our May 5,
1995 dismissal of its protest against the intended award by the
Department of the Army, Army Materiel Command, of a sole source
contract to Barnes & Reinecke, Inc. (BRI), and (2) protests the
subsequently issued solicitation--request for proposals (RFP)
No. DAAE20-95-R-0101--for a sole source award to BRI, for engineering
support services related to the M109 self-propelled howitzer. The
Army justifies the proposed sole source award to BRI on the basis that
only BRI can provide the services without unacceptable delays and
substantial duplication of costs that will not be recovered through
competition. Nomura challenges both of these conclusions.
We dismiss the request for reconsideration as academic and deny the
protest.
BACKGROUND
The M109 howitzer provides artillery support to armored/mechanized
infantry divisions for the Army and several foreign military sales
customers. The services being procured include: engineering and
maintenance of the M109 technical data package, technical manuals, and
depot maintenance work requirements; development and incorporation of
engineering change proposals; engineering studies; failure analysis;
and life-cycle engineering.
The original "class" justification and approval (J&A) for use of other
than full and open competitive procedures concluded that a sole source
award to BRI was justified under the authority of 10 U.S.C.
2304(c)(1), on the basis that the firm was the only known source that
could supply the services. It provided that BRI was to perform the
services for a period of approximately 5 years. The J&A recognized
Nomura as an interested source, but concluded that the firm would need
at least an 18- to 24-month start-up period, a delay the M109 program
could not then accommodate.
On March 21, 1995, a synopsis of the intended award to BRI was
published in the Commerce Business Daily (CBD). On April 3, Nomura
protested the sole source procurement, alleging that it could perform
the work based on its past performance of a technical support contract
for the M110 self-propelled howitzer. (At the time of the protest,
the firm did not have a copy of the J&A, and thus did not specifically
challenge it.) On May 5, we dismissed Nomura's protest (B-260977) as
premature, based on the agency's representation that the sole source
award to BRI was under consideration and had not yet received the
necessary approvals. If and when the procurement approval was made on
a sole source basis, the Army indicated it intended to resynopsize the
procurement in the CBD. In response, Nomura first requested
reconsideration of our dismissal and then, after issuance of the
solicitation for a sole source award to BRI, protested the agency's
rationale for a sole source procurement.
Subsequently, on August 3, the Army issued amendment No. 1 to the
original class J&A. The amended J&A concluded that a sole source
award to BRI, the developer of the M109 howitzer, was necessary
because a competitive procurement would result in program delays of 6
to 10 months and duplication of costs not expected to be recovered
through competition in the amount of $2,000,000. The amendment
decreased the dollar value of the contract contemplated in the
original J&A by almost half and the 5-year term of the original J&A to
1 year plus two 6-month options. It also provided for competition for
future M109 engineering services in the near future; the agency
expects to issue a competitive solicitation by February 1996 and
estimates a resulting award by October 1996.
Full decision text continues on ProtestIntel...