M.E.E., Inc.
Case: B-265605.3
Agency:
Protester: M.E.E., Inc.
Date: 1996-02-22
Denied
M.E.E., Inc.
BNUMBER: B-265605.3; B-265605.4
DATE: February 22, 1996
TITLE: M.E.E., Inc.
**********************************************************************
Matter of:M.E.E., Inc.
File: B-265605.3; B-265605.4
Date: February 22, 1996
Donald A. Tobin, Esq., Thomas J. Touhey, Esq., and Lori Ann Lange,
Esq., Bastianelli, Brown, Touhey, & Kelley, for the protester.
Lt. Col. Richard W. Tobin II, and Kathryn M. Burke, Esq., Department
of the Air Force, for the agency.
Henry J. Gorczycki, Esq., and Guy R. Pietrovito, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Where a solicitation's required Davis-Bacon Act wage determination
is revised after submission of proposals but prior to award, the
contracting agency properly proposes to amend the solicitation to
incorporate the revised determination and reopen the competition to
permit submission of revised proposals.
2. Where an agency proposes to amend a solicitation and reopen the
competition on bases that are not the subject of a protest, the
proposed action is not corrective action in response to a protest and
the protester is not entitled to reimbursement of its protest costs.
DECISION
M.E.E., Inc. protests the reopening of discussions under request for
proposals (RFP) No. F02604-94-R0010, issued by the Department of the
Air Force for maintenance, repair, and minor construction services
under the simplified acquisition of base engineering requirements at
Luke Air Force Base, Gila Bend Air Force Auxiliary Field, and Fort
Tuthill Recreation Area, Flagstaff, Arizona. M.E.E. also claims
entitlement to protest costs under this and two earlier protests filed
against a contract awarded to PI Construction Corporation.
We deny the protest and the claim.
The RFP, issued on October 25, 1994 as a total set-aside for small
disadvantaged businesses (SDB), contemplated award of an indefinite
delivery/indefinite quantity, fixed-price task order contract. The
RFP provided for award on a best value basis and stated that technical
merit and price were of equal importance.
Offerors were required to propose prices in terms of a coefficient of
the "Means price," which is determined from standardized prices for
construction work published in the Means cost book. Under this
pricing method, the sum of labor and materials is adjusted to reflect
the Phoenix City Cost Index and minimum wage rates specified under the
Davis-Bacon Act, 40 U.S.C. sec. 276a (1994), to produce the Means price.
The Means price for work performed under the contract will be
multiplied by the contractor's proposed price coefficient to ascertain
the price to be paid the contractor for work performed. Thus, an
offeror proposing a coefficient of 1.0 offers to perform the contract
at the Means price, while a proposed coefficient greater than 1.0 or
less than 1.0 is an offer to perform at a price greater than or less
than the Means price, respectively.
After the conduct of discussions and evaluation of best and final
offers (BAFO), the Air Force awarded a contract to PI as representing
the best value to the government. PI's proposal was higher-rated
technically and was priced higher than M.E.E.'s.
On August 4, 1995, M.E.E. protested the award to PI to our Office on
the following bases (hereafter, the "first protest"):
"A. The Air Force failed to give equal weight to cost and
technical criteria[;]
"B. Air Force improperly penalized M.E.E. for providing a price
below the coefficient[;]
"C. The Air Force failed to hold meaningful discussions with
M.E.E.[;]
"D. The Air Force improperly gave credit to capabilities not
required by the solicitation[.]"
M.E.E. also protested PI's SDB status to the Small Business
Administration (SBA). On September 13, 1995, at about the time the
Air Force submitted its report on M.E.E.'s first protest, the SBA
determined that PI did not qualify as an SDB concern for this
procurement. On September 15, M.E.E. submitted two additional protest
bases (hereafter, the "second protest") to our Office, challenging the
award to PI because the SBA had determined that PI was not an SDB
concern, and objecting to the Air Force's evaluation of M.E.E.'s
proposed price coefficient.
On September 29, the Air Force terminated PI's contract based upon the
SBA's determination that the contractor was not an SDB concern. On
October 3, the Air Force notified our Office of the termination,
stating that it was amending the RFP and would reopen discussions and
request revised BAFOs.
On October 5, M.E.E. protested the Air Force's proposed amendment of
the RFP and reopening of negotiations (hereafter, the "third
protest"). M.E.E.
Full decision text continues on ProtestIntel...