Eastco Building Services, Inc.
Case: B-265851
Agency:
Protester: Eastco Building Services, Inc.
Date: 1995-12-29
Denied
Eastco Building Services, Inc.
BNUMBER: B-265851; B-265851.2
DATE: December 29, 1995
TITLE: Eastco Building Services, Inc.
**********************************************************************
Matter of:Eastco Building Services, Inc.
File: B-265851; B-265851.2
Date: December 29, 1995
Robert M. Cambridge, Esq., for the protester.
Cynthia S. Guill, Esq., Diane D. Hayden, Esq., and Patrick J. Coll,
Esq., Department of the Navy, for the agency.
Scott H. Riback, Esq., and David A. Ashen, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest against agency's refusal to permit upward correction of firm's
bid is denied where bidder's worksheets show that a mistake was made
but do not establish the firm's intended bid for the allegedly omitted
cost element.
DECISION
Eastco Building Services, Inc. protests the Department of the Navy's
refusal to allow the firm to correct a mistake in its bid submitted in
response to invitation for bids (IFB) No. N00187-94-B-8127, for the
repair and maintenance of air conditioning equipment at various
locations around Norfolk, Virginia. Eastco challenges the Navy's
determination that the firm failed to establish its intended bid.
We deny the protest.
The IFB contained a total of 47 line items. For line item Nos. 0001
and 0002, which are the subject of Eastco's protest, bidders were
required to submit prices for the performance of service calls that
would require no more than 16 hours of labor and $250 in material
costs; bidders were to submit lump-sum unit and extended prices for an
estimated quantity of 200 service calls performed during regular
business hours (item 0001) and separate lump-sum unit and extended
prices for an estimated quantity of emergency service calls performed
after regular business hours (item 0002). All but one of the
remaining line items called for the performance of periodic tasks,
such as monthly inspections or winter overhauls of particular
equipment; bidders were required to submit lump-sum unit and extended
prices for each of these other line items which included the cost of
materials associated with performance of the required task. The
remaining line item, No. 0024, was divided into 15 subline items which
called for bidders to submit loaded hourly rates for various
categories of labor; material costs associated with these services
were not to be included in these rates, but instead were included as
part of an IFB estimate of $700,000 for material costs under item
0024.
In response to the contracting officer's request that it review its
bid for possible mistakes, Eastco advised the agency that it had made
a mistake in its calculations for line item Nos. 0001 and 0002.
Eastco claimed that it did not include in its prices for these items
the cost of materials required for the service calls, and based its
bid instead on only the labor costs associated with the service calls.
Eastco requested that it be permitted to adjust its bid upward to
reflect an additional $250 per service call--that is, the maximum
material cost for which the contractor would be responsible--for a
total upward correction of $100,000 ($250 multiplied by the IFB's
estimated 400 regular and emergency service calls). In support of its
request for correction, Eastco submitted an "original worksheet" for
the two items--two undated, handwritten sheets, along with two undated
typewritten versions of the same calculations (Eastco included an
original and typewritten worksheet for each of the line items in
dispute). None of these worksheets, however, included the material
costs of $250 per service call. Instead, they presented what Eastco
claimed were the calculations of its loaded hourly rates for
performing the service calls, including direct labor costs, travel,
uniforms, equipment, payroll benefits, subcontractor costs, general
and administrative (G&A) costs and profit.
The agency concluded that Eastco's worksheets, while showing that the
firm had made a mistake, did not clearly show its intended bid. The
agency therefore made several requests for additional information. In
response to the Navy's first request, Eastco again submitted two
undated, handwritten worksheets and two typewritten worksheets,
claiming that these were the same exhibits that had been previously
submitted. An examination of this set of handwritten worksheets,
however, shows that although they contain the same calculations as
those appearing on the originally submitted handwritten worksheets,
they are not copies of the same documents. This set of worksheets
also did not include any provision for material costs. In responding
to the Navy's second request for additional information, Eastco
provided copies of computer-generated worksheets for all line items
except Nos. 0001 and 0002.
Full decision text continues on ProtestIntel...