Morrison Construction Services
Case: B-266233
Agency:
Protester: Morrison Construction Services
Date: 1996-01-26
Denied
Morrison Construction Services
BNUMBER: B-266233; B-266234
DATE: January 26, 1996
TITLE: Morrison Construction Services
**********************************************************************
Matter of:Morrison Construction Services
File: B-266233; B-266234
Date: January 26, 1996
John Chapman for the protester.
Gerald J. Brentnall, Jr., Esq., Rowley, Grace, Brentnall & Kraft, for
Farinha, Inc., an interested party.
Calvin F. Boles IV, Esq., and Cynthia S. Guill, Esq., Department of
the Navy, for the agency.
Susan K. McAuliffe, Esq., and Michael R. Golden, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Where bidder has submitted only photocopies of required bid guarantee
documents as of the time of bid opening, the bid guarantees are of
questionable enforceability and the bids were properly rejected as
nonresponsive; since responsiveness cannot be established after bid
opening, the defect in the bid guarantees cannot be cured by the
submission of the original bid guarantee documents after bid opening.
DECISION
Morrison Construction Services protests the agency's rejection of its
apparent low bids, and the award of contracts to Farinha, Inc., under
invitations for bids (IFB) Nos. N62766-95-B-0402 and N62766-95-B-0403,
issued by the Department of the Navy for the replacement of air
conditioning and heat recovery units at a family housing area in Guam.
Morrison challenges the agency's determination that the bid guarantees
submitted with the protester's bids were defective because they were
photocopies of required bid guarantee documents.
We deny the protests.
Each IFB required the submission of a bid guarantee in the amount of
20 percent of the bid price. The IFBs' instructions provided that all
bids and bonds were to be submitted in "original format" and stated
that bids must be manually signed. Other than providing for the
timely transmission by facsimile of acknowledgment of amendments, the
IFBs did not expressly authorize facsimile bids or modifications. Six
bids were received by bid opening on August 17, 1995. Morrison's
apparent low bids were rejected, by letter of September 14, for
including only photocopies of the required bid bond documents. Awards
were made to Farinha, the next low bidder, under the IFBs. These
protests followed.
Morrison explains that it mailed its bids, including the original bid
bonds and power of attorney certificates, by certified mail on Friday,
August 11 (5 days before the scheduled bid opening). On Monday,
August 14, upon learning that 5 days may not be sufficient time for
receipt at the Guam bid openings, it sent a copy of the bids to its
agent in Guam; that agent submitted the photocopied bids with notes
from Morrison explaining, as stated above, why the photocopies of its
bids were being submitted. Morrison's original bid documents were
received by the agency on August 25, 8 days after bid opening.
Morrison contends that the bond documents are sufficient since they
show that the surety was bound at the time of bid opening, that any
perceived deficiency due to the photocopy nature of the bond documents
should be waived as a minor informality, and that the agency could
confirm after award that there were no alterations to the photocopied
bond documents since the original bond documents were sent to the
agency prior to bid opening.
A bid bond is a form of bid guarantee designed to protect the
government's interest in the event of default; that is, if a bidder
fails to honor its bid in any respect, the bid bond secures a surety's
liability for all reprocurement costs. Ray Ward Constr. Co.,
B-256374, June 14, 1994, 94-1 CPD para. 367. As such, a required bid bond
is a material condition of an IFB with which there must be compliance
at the time of bid opening; when a bidder submits a defective bid
bond, the bid itself is rendered defective and must be rejected as
nonresponsive. Blakelee, Inc., B-239794, July 23, 1990, 90-2 CPD para.
65. The determinative question as to the acceptability of a bid bond
is whether the bid documents at the time of bid opening establish that
the bond is enforceable against the surety should the bidder fail to
meet its obligations. If the agency cannot determine definitely from
the documents submitted with the bid that the surety would be bound,
the bid is nonresponsive and must be rejected. Global Eng'g,
B-250558, Jan. 11, 1993, 93-1 CPD para. 31. Photocopies of bid guarantee
documents generally do not satisfy the requirement for a bid guarantee
since there is no way, other than by referring to the originals after
bid opening, for the contracting agency to be certain that there had
not been alterations to which the surety had not consented, and that
the government would therefore be secured. The King Co., Inc.,
B-228489, Oct. 30, 1987, 87-2 CPD para.
Full decision text continues on ProtestIntel...