Brown & Root, Inc. and Perini Corp., a joint venture
Case: B-270505.2
Agency: Department of State
Protester: Brown & Root, Inc. and Perini Corp., a joint venture
Date: 1996-09-12
Denied
Brown & Root, Inc. and Perini Corp., a joint venture
BNUMBER: B-270505.2; B-270505.3
DATE: September 12, 1996
TITLE: Brown & Root, Inc. and Perini Corp., a joint venture
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
A protected decision was issued on the date below and was subject to a
GAO Protective Order. This version has been redacted or approved by
the parties involved for public release.
Matter of:Brown & Root, Inc. and Perini Corp., a joint venture
File: B-270505.2; B-270505.3
Date:September 12, 1996
Rand L. Allen, Esq., Paul F. Khoury, Esq., Christopher R. Yukins,
Esq., and Phillip H. Harrington, Esq., Wiley, Rein & Fielding, for the
protester.
Kathleen C. Little, Esq., David R. Johnson, Esq., Robert J. Rothwell,
Esq., McDermott, Will & Emery, for H.B. Zachry Company, The Parsons
Corporation, and Sundt Corp., a joint venture, the intervenor.
Dennis J. Gallagher, Esq., Department of State, for the agency.
John L. Formica, Esq., and James A. Spangenberg, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Where agency brought principal concerns about the protester's
proposal to the attention of the protester and since various other
weaknesses, both individually and in toto, did not prevent the
protester from having a reasonable chance for award, the agency's
failure to point out those other weaknesses did not deprive the
protester of meaningful discussions; agency was not required to hold
discussions regarding every weakness identified in the protester's
proposal.
2. Where a solicitation lists evaluation factors and subfactors in
descending order of importance, each factor listed and each subfactor
within each factor is of decreasing weight; such an evaluation scheme
does not indicate that the subfactors of lower-weighted factors are
necessarily of less individual weight than subfactors of
higher-weighted factors.
3. Agency scoring and weighting method used to evaluate and rank
offers was consistent with the evaluation scheme stated in the
solicitation and did not produce an irrational award selection result.
4. Protester was not prejudiced by the agency's alleged waiver of a
requirement that potential offerors have certain security clearances
by an established date where the record does not evidence that had the
protester been aware of the allegedly relaxed requirement, it would
have submitted a different proposal that would have had a reasonable
possibility of award.
DECISION
Brown & Root, Inc. and Perini Corporation, a joint venture, protest
the award of a contract to H.B. Zachry Company, The Parsons
Corporation, and Sundt Corp., a joint venture (ZPS), under request for
proposals (RFP) No. MEBCO-95-R-0300, issued by the Department of State
to construct secure chancery facilities for the United States Embassy
in Moscow, Russia. Brown/Perini argues that the agency failed to
conduct meaningful discussions, did not follow the evaluation criteria
set forth in the solicitation in evaluating proposals and selecting
ZPS' higher-priced proposal, and waived the requirement that all joint
venture partners possess a top secret facility clearance by a certain
date.
We deny the protest.
Construction began on a new embassy compound in Moscow in 1979. The
compound encompasses eight buildings on a 10-acre site. Construction
has been completed on seven of the buildings, and these buildings are
currently occupied. The subject of this procurement, the New Office
Building (NOB), is partially complete and, as presently constructed,
is eight stories tall with a penthouse. Construction of the NOB was
halted in 1985 when it was discovered that clandestine listening
devices had been installed in the NOB's framework. Under the
circumstances, the agency determined that security for the design and
reconstruction of the NOB is critical.[1]
The work required under the RFP includes the completion of
design/construction documentation for the NOB; the complete demolition
of a nearby building and demolition of the NOB from the eighth floor
to the sixth floor; the construction of a steel frame structure on top
of the NOB's sixth floor slab through a tenth floor and penthouse; the
completion of the NOB below the sixth floor; and the revision and
upgrading of the building core to include, among other things, new
heating, ventilation and air conditioning (HVAC), plumbing, and
electrical systems.
Full decision text continues on ProtestIntel...