McCaffery & Whitener, Inc.
Case: B-270814
Agency:
Protester: McCaffery & Whitener, Inc.
Date: 1996-04-25
Denied
McCaffery & Whitener, Inc.
BNUMBER: B-270814; B-270814.2
DATE: April 25, 1996
TITLE: McCaffery & Whitener, Inc.
**********************************************************************
Matter of:McCaffery & Whitener, Inc.
File: B-270814; B-270814.2
Date:April 25, 1996
Thomas F. McCaffery for the protester.
Richard S. Haynes, Esq., Department of the Navy, for the agency.
Robert C. Arsenoff, Esq., and Paul I. Lieberman, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Agency properly did not consider transition costs in selecting
awardee where solicitation did not provide for the evaluation of such
costs.
2. Agency evaluation of awardee's technical proposal which did not
take into account the need for a phase-in training period is
unobjectionable where phase-in training was neither a requirement nor
an evaluation factor.
3. Protest that agency should have rejected awardee's offer as
presenting an unacceptable cost risk because it contained
disproportionate prices for two labor categories is denied where
agency reasonably concluded that the government could control the
labor mixes to be used in the issuance of delivery orders.
DECISION
McCaffery & Whitener, Inc. (MWI) protests the award of a contract to
Global Associates, Ltd. under request for proposals (RFP) No.
N62387-96-D-3017, issued by the Department of the Navy for maritime
related engineering, technical and analytical services. MWI alleges
that the agency failed to evaluate transition costs in selecting
Global for award and that the agency misevaluated Global's technical
and price proposals.
We deny the protests.
The RFP, issued on July 17, 1995, contemplated the award of a 1-year
indefinite quantity contract (with 1 option year) with provisions for
both fixed-price and time- and-materials delivery orders to be issued
by the Navy. Award was to be made to the offeror submitting the low
technically acceptable proposal.
Technical acceptability was to be measured against four factors listed
in descending order of importance: technical approach/understanding;
personnel; management; and facilities/resources. Price was to be
evaluated by multiplying fixed labor rates submitted by offerors for
five labor categories by the estimated labor hours associated with
each category.
Three initial proposals were received and one was eliminated, after
which discussion were conducted with MWI and Global, the remaining
competitive range offerors. Following discussions, each offeror
submitted a best and final offer (BAFO), both of which were found to
be technically acceptable. Global's evaluated price was $692,115;
MWI's was $699,730. Global received the award as the result of its
lower price and this protest followed.
The protester's first two bases of protest relate to a transfer plan
proposed in the event that MWI did not receive the award. Under the
predecessor contract, MWI was required to return software and hardware
used during contract performance so that relevant materials could then
be provided to the successful contractor. Prior to the submission of
BAFOs, MWI--the incumbent contractor--wrote the Navy proposing a
transition plan.
Following notice of the award to Global, MWI again wrote the Navy
outlining the details of its proposed transition plan over a 30-day
period at a cost of $40,078.50. The Navy submitted a counterproposal
for a plan to be executed over a 2-week period at a cost of
$8,674.40. In particular, the Navy envisioned MWI performing the
following tasks:
"-- Review of existing data bases
-- Ship Data Base
-- Ship Access to Ports Evaluator,
-- Ship Availability Generator, and
-- the Merchant Marine Manpower Model
"Review shall include data base familiarization, critical
assumptions, critical elements and data base maintenance."
MWI submitted another slightly scaled-down proposal at a cost of
$30,583.60; negotiations have been suspended in light of the stay of
contract performance occasioned by this protest.
Noting that there is a $7,615 difference in prices offered between
Global and MWI, the protester first asserts that, since the Navy's
estimate of transition costs ($8,674) is greater than the price
difference, MWI's proposal reflects the lowest cost to the
government and, accordingly, MWI should receive the award. Transition
costs may be an evaluation factor in appropriate circumstances, but an
agency may only evaluate them if offerors are advised in the RFP that
such costs will be evaluated. Since the RFP in this case did not so
advise offerors, there was no basis for the agency to consider
transition costs in determining the low cost offeror. Cherokee Elecs.
Corp., B-240659, Dec. 10, 1990, 90-2 CPD para.
Full decision text continues on ProtestIntel...