Christie Constructors, Inc.
Case: B-271759
Agency:
Protester: Christie Constructors, Inc.
Date: 1996-07-23
Denied
Christie Constructors, Inc.
BNUMBER: B-271759; B-271759.2
DATE: July 23, 1996
TITLE: Christie Constructors, Inc.
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
A protected decision was issued on the date below and was subject to a
GAO Protective Order. This version has been redacted or approved by
the parties involved for public release.
Matter of:Christie Constructors, Inc.
File: B-271759; B-271759.2
Date:July 23, 1996
Hiram S. Dillin, Esq., and David J. Bader, Esq., Dillin & Bader, Inc.,
for the protester.
Justin P. Patterson, Esq., and James L. Weiner, Esq., Department of
the Interior, for the agency.
Andrew T. Pogany, Esq., and Michael R. Golden, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. In reviewing an agency's evaluation, the General Accounting Office
will not reevaluate proposals but instead will examine the agency's
evaluation to ensure that it was reasonable and consistent with the
stated evaluation criteria. An offeror is responsible for providing a
full discussion of its technical approach and methodology within the
four corners of the proposal.
2. Protests based upon alleged solicitation improprieties which are
apparent prior to the time set for receipt of initial proposals must
be filed prior to the initial closing. Protesters do not have the
option of simply making unilateral assumptions regarding the meaning
of conflicting or patently ambiguous provisions in a solicitation and
then expect relief when the agency does not act in the manner the
protester assumed.
3. In the absence of a timely objection to the solicitation's award
methodology, award may be made consistent with the agency's reasonable
interpretation of the request for proposal award provisions.
DECISION
Christie Constructors, Inc. protests the exclusion of its proposal
from the competitive range and the award of a contract to Dillingham
Construction N.A., Inc. under request for proposals (RFP) No.
1425-6-SP-20-03730, issued by the U.S. Bureau of Reclamation,
Sacramento, California for the installation of a new spillway gate and
repair of seven other gates at Folsom Dam, California. The agency
excluded Christie's proposal because it did not contain sufficient
technical information to substantiate Christie's ability to accomplish
the RFP requirements.
We deny the protest.
This contract was the last of four contracts awarded by the agency on
an emergency basis following the failure of spillway gate No. 3 in
July 1995, a failure that resulted in the uncontrolled release of
water into the American River which endangered downstream
communities.[1] Accordingly, because gate failures could occur in the
absence of additional repairs under reasonably foreseeable storm
conditions, the agency executed a Justification for Other than Full
and Open Competition (J&A), pursuant to Federal Acquisition Regulation
(FAR) sec. 6.302-2, and solicited offers only from eight pre-selected
construction firms, including the protester and Dillingham.[2]
The RFP, issued March 12, 1996, required the submission of initial
proposals by April 9; as stated above, because of the urgent nature of
the work, the agency contemplated making an immediate award after
receipt of initial proposals. In fact, the RFP itself stated that
"[i]t is anticipated that the Notice to Proceed for [the work] will be
issued on April 15, 1996."[3] The RFP contemplated a fixed-price
contract and stated that award would be made to either "the lowest
price 'acceptable' offer[or] or [to an] acceptable offer[or], the
price or cost of which is not the lowest, but which is sufficiently
more advantageous than the lowest price [offeror] so as to justify the
payment of higher price or cost."[4] The RFP, among other things,
required that technical proposals address: (1) safety provisions for
workers; (2) list of major equipment and key support equipment to be
used; (3) procedures to maintain access to the seven existing gates
through completion of each phase of construction; (4) procedures to
install the new gate, including, as a minimum, a brief discussion of
the sequence of frame construction; (5) containment of hazardous
materials; (6) procedures for rotating the "trunnion pins"; (7)
procedures for maintaining the required openings of Folsom Dam Road;
(8) a preliminary bar chart showing the construction sequencing,
durations, including start and finish dates, for 25 schedule items
listed in the RFP; and (8) personnel resumes. Section M of the RFP
also advised offerors as follows:
"Notice is given of the possibility that an award may be made
after receipt of initial proposals without further discussions or
negotiations.
Full decision text continues on ProtestIntel...