Sigmatech, Inc.
Case: B-271821
Agency: Department of Defense : Defense Information Systems Agency
Protester: Sigmatech, Inc.
Date: 1996-08-22
Denied
Sigmatech, Inc.
BNUMBER: B-271821; B-271821.2
DATE: August 22, 1996
TITLE: Sigmatech, Inc.
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
A protected decision was issued on the date below and was subject to a
GAO Protective Order. This version has been redacted or approved by
the parties involved for public release.
Matter of:Sigmatech, Inc.
File: B-271821; B-271821.2
Date:August 22, 1996
Rand L. Allen, Esq., Paul F. Khoury, Esq., and David A. Vogel, Esq.,
Wiley, Rein & Fielding, for the protester.
Joshua A. Kranzberg, Esq., and Carol P. Rosenbaum, Esq., Department of
the Army, for the agency.
Glenn G. Wolcott, Esq., and Paul Lieberman, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Agency reasonably determined that offerors were required to have
experience with particular weapon systems supported by contract, and
protester's assertion that its experience with other weapon systems
should have been considered equivalent reflects mere disagreement with
the agency's judgment.
2. Agency reasonably concluded that overall level of personnel
proposed by protester was inadequate to meet the government's
requirements under a task order contract where protester's proposed
staffing level was based on the unrealistic assumption that the
government's requirements would be met through a steady-state level of
effort equal to an average of the total contract requirements.
3. Where awardees each proposed over three times more personnel with
demonstrated experience supporting the weapons systems to be supported
by this contract than did the protester, and solicitation provided
that an offeror's evaluated capabilities to perform the contract
requirements was significantly more important than any other
evaluation factor, there is no basis to conclude that protester's
slightly lower-cost proposal offered greater value to the government
than awardees' proposals.
4. Where solicitation provided that failure to demonstrate relevant
experience would be a negative evaluation factor, agency's advice
during pre-proposal conference that offerors' abilities to
affirmatively demonstrate such experience would be an enhancement did
not mislead offerors so as to warrant sustaining the protest.
DECISION
Sigmatech, Inc. protests the Department of the Army's contract awards
to Dynamics Research Corporation (DRC), Decisions and Advanced
Technology Associates, Inc. (DATA) and System Dynamics International,
Inc. (SDI) under request for proposals (RFP) No. DAAJ09-95-R-0608.
The RFP sought support services for the Army's Aviation and Troop
Command (ATCOM) and Program Executive Office (PEO) in connection with
the Programmatic and Technical Support (PATS) III program. Sigmatech
maintains that the agency improperly evaluated its proposal as
unacceptable, and asserts that its proposal should have been assessed
as offering greater value to the government than those of the
awardees.
We deny the protest.
BACKGROUND
On September 22, 1995, the Army issued the solicitation at issue
here.[1] The RFP contemplated the award of multiple
cost-reimbursement task order contracts to provide programmatic
support for specified ATCOM/PEO weapons systems. Specifically, the
RFP stated: "the Government contemplates up to three awards (full and
open, small business, 8a),"[2] and established a minimum value of
$300,000 and an estimated maximum value of $33 million for each
contract.
Section M of the RFP states that proposals would be evaluated in three
areas--capabilities, past performance, and cost--and that capabilities
were significantly more important than past performance, which was, in
turn, more important than cost. Regarding evaluation of offerors'
capabilities, section M states:
"This Evaluation Area is used to gauge the Government's
perception of the ability of a Contractor to successfully
complete the diverse and potentially complex work likely to be
tasked under the SOW in support of multiple weapon systems set
forth in Attachment 2."[3]
Section M further established three factors to be considered in
evaluating offerors' capabilities: corporate capabilities, corporate
historical experience, and key personnel. With regard to key
personnel, the RFP required offerors to submit resumes for the prime
and subcontractor personnel being proposed, stating that up to 200
resumes could be submitted.
Full decision text continues on ProtestIntel...