PW Construction, Inc.
Case: B-272248
Agency:
Protester: PW Construction, Inc.
Date: 1996-09-13
Denied
PW Construction, Inc.
BNUMBER: B-272248; B-272248.2
DATE: September 13, 1996
TITLE: PW Construction, Inc.
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
A protected decision was issued on the date below and was subject to a
GAO Protective Order. This version has been redacted or approved by
the parties involved for public release.
Matter of:PW Construction, Inc.
File: B-272248; B-272248.2
Date:September 13, 1996
Timothy A. Sullivan, Esq., Starfield & Payne, for the protester.
James G. Ehlers, Esq., Hillyer & Irwin, for C.E. Wylie Construction
Company, an intervenor.
Christopher M. Bellomy, Esq., Edward B. Hanel, Esq., and George N.
Brezna, Esq., Department of the Navy, for the agency.
Peter A. Iannicelli, Esq., and Michael R. Golden, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Protest that the agency gave preferential treatment to the awardee
in its evaluation of proposals is denied where the record shows that
the evaluation was reasonable and consistent with the request for
proposals's evaluation scheme, and the agency fairly evaluated both
the protester's and the awardee's proposals.
2. Award of a contract to the offeror of the higher technically
rated, higher-priced proposal was proper where the agency reasonably
determined that the awardee's slightly higher-priced proposal was
worth the additional cost.
DECISION
PW Construction, Inc. protests the Navy's award of a fixed-price
construction contract to C.E. Wylie Construction Company pursuant to
request for proposals (RFP) No. N62474-94-R-7479. The protester
contends that the Navy gave preferential treatment to Wylie when
evaluating proposals and that the Navy's evaluation of proposals was
not consistent with the RFP's evaluation scheme. The protester also
contends that it should have been awarded the contract because its
proposed total price was lower than Wylie's.[1] We deny the protest.
Issued on March 4, 1996, the RFP solicited proposals for demolition of
existing structures and construction of three dormitories and two
mechanical buildings at Travis Air Force Base[2] and contained
detailed drawings and specifications concerning the buildings to be
constructed. The RFP stated that the contract would be awarded to the
offeror whose conforming offer was determined to be most advantageous
to the government after consideration of price and other factors.
Eight proposals were received by the April 10 closing date for
submission of initial proposals. After evaluation, seven proposals
were included in the competitive range. Because all offers were
priced at more than the available funding, the Navy took several
actions aimed at ensuring that the project would be completed within
available funding constraints. The Navy had its project
architect/engineer review the project to determine whether any
potential savings could be identified. The Navy also asked the Air
Force to provide additional funding; the Air Force complied. In
addition, during discussions, competitive range offerors were asked
for their recommendations for deleting requirements in order to lessen
the overall cost. After considering potential cost-saving measures
from all sources, the Navy issued amendment 0004 requesting best and
final offers (BAFO), deleting a large number of requirements,
modifying others, and generally reducing the scope of the project.
BAFOs were received by May 10 and were evaluated by the source
selection board (SSB). The SSB gave Wylie's BAFO an overall rating of
[deleted] and PW's BAFO an overall rating of [deleted]. Wylie's total
proposed price ($16,217,472) was the second lowest-priced proposal and
PW's total proposed price of [deleted] was the lowest.[3] Based on
Wylie's BAFO's superior technical rating, the SSB recommended that
Wylie be awarded the contract. The source selection authority (SSA)
concurred, and the contract was awarded to Wylie on June 4. After a
debriefing by the agency, PW filed its initial protest in our
Office.[4]
Essentially, PW contends that the Navy's evaluation of proposals and
award decision were flawed. The protester alleges that Wylie's
proposal received higher ratings as the result of preferential
treatment by the SSB. The protester also asserts that the Navy gave
greater weight to technical evaluation factors than to price and that
the SSA failed to conduct a cost/technical tradeoff analysis.
According to PW, a proper cost/technical tradeoff analysis would have
resulted in award of the contract to PW on the basis of its
lower-priced proposal.[5]
The evaluation of proposals is primarily within the discretion of the
procuring agency, not our Office; the agency is responsible for
defining its needs and the best means of accommodating them and must
bear the consequences of a defective evaluation.
Full decision text continues on ProtestIntel...