Highlights
The bid is ambiguous as to the offered bid acceptance period. Is therefore nonresponsive. Bid opening was on August 1. Sundt was the low bidder. Maintains that one reasonable interpretation is that Sundt offered a 90-day bid acceptance period. Sundt's bid was ambiguous. Sundt asserts that the Ingram decision is inapplicable here because Sundt not only acknowledged the amendment changing the bid acceptance period on the unrevised SF 1442. Its bid was therefore responsive. We believe the protester's reliance on the Walsky decision is misplaced and that the Ingram decision is controlling here. The agency erroneously inserted "10" in the bid acceptance period blank in the solicitation which is normally to be completed by the bidder.
View Decision
Matter of: Sundt Corporation File: B-274203 Date: November 5, 1996
Where bidder acknowledges solicitation amendment changing the minimum bid acceptance period from 90 to 120 calendar days, but inserts 90 in the bid form blank for proposing an acceptance period, the bid is ambiguous as to the offered bid acceptance period, a material solicitation requirement, and is therefore nonresponsive.
Attorneys
DECISION
Sundt Corporation protests the rejection of its bid as nonresponsive under invitation for bids (IFB) No. 68711-94-B-1587, issued by the Department of the Navy for certain construction at the Marine Corps Air Station at Miramar, California.
We deny the protest.
The Navy issued the IFB on July 1, 1996, with a minimum bid acceptance period of 90 calendar days. Amendment No. 0001, issued July 18, changed, among other things, the minimum bid acceptance period to 120 calendar days. Bid opening was on August 1, and Sundt was the low bidder. In its bid, Sundt inserted 90 days in the blank provided on Standard Form (SF) 1442 as its bid acceptance period and included an acknowledgment of the amendment that changed the minimum bid acceptance period to 120 days.
The Navy, while recognizing that Sundt had acknowledged amendment No. 0001, rejected Sundt's bid as nonresponsive because it failed to offer the required 120-day bid acceptance period. The Navy, relying on our decision John P. Ingram, Jr. & Assocs., Inc., B-250548, Feb. 9, 1993, 93-1 CPD Para. 117, maintains that one reasonable interpretation is that Sundt offered a 90-day bid acceptance period, and that at best, Sundt's bid was ambiguous.
Sundt asserts that the Ingram decision is inapplicable here because Sundt not only acknowledged the amendment changing the bid acceptance period on the unrevised SF 1442, but it included in its offer the actual amendment itself, executed by its authorized agent. Sundt cites Walsky Constr. Co., et al., B-216571 et al., May 17, 1985, 85-1 CPD Para. 562 to support its position that acknowledgment of the amendment clearly evidenced its intent to offer the required 120-day bid acceptance period, and its bid was therefore responsive.
We believe the protester's reliance on the Walsky decision is misplaced and that the Ingram decision is controlling here. In Walsky, the agency erroneously inserted "10" in the bid acceptance period blank in the solicitation which is normally to be completed by the bidder. This resulted in an obvious discrepancy with another solicitation provision stating that bids offering less than 30 days for acceptance would be rejected. The agency then issued an amendment changing the bid acceptance period to 60 days. This amendment was acknowledged by the low bidder, but the bid was submitted on the original incorrect form. We found that the bid was not ambiguous, and that it was reasonable to assume that because the low bidder acknowledged the amendment, it intended to comply with the amended 60-day bid acceptance period requirement, and the use of the unamended form was merely an oversight.
In the present case, as in Ingram, the bidder acknowledged the amendment extending the bid acceptance period to 120 days, but also inserted the number 90 in the blank on the bid form in the block which permits a bidder to designate an alternate bid acceptance period. Thus, unlike the situation in Walsky, here the bidder rather than the agency made the entry which led the Navy to doubt whether the bid provided a 120-day bid acceptance period.
To be responsive, a bid must show on its face at the time of bid opening that it is an unqualified offer to comply with all the material requirements of the solicitation, and that the bidder intends to be bound by the government's terms as set forth in the solicitation. M&G Servs., Inc., B-244531, June 27, 1991, 91-1 CPD Para. 612. The bid acceptance period is one of the material IFB requirements. General Elevator Co., Inc., B-226976, Apr. 7, 1987, 87-1 CPD Para. 385.
Full decision text continues on ProtestIntel...