MCI Constructors, Inc.
Case: B-274347
Agency: Department of Defense : Department of the Navy : Naval Facilities Engineering Command
Protester: MCI Constructors, Inc.
Date: 1996-12-03
Denied
MCI Constructors, Inc.
BNUMBER: B-274347; B-274347.2
DATE: December 3, 1996
TITLE: MCI Constructors, Inc.
**********************************************************************
Matter of:MCI Constructors, Inc.
File: B-274347; B-274347.2
Date:December 3, 1996
Steven J. Weber, Esq., Watt, Tieder & Hoffar, for the protester.
Christopher M. Bellomy, Esq., George N. Brezna, Esq., and Robert M.
Roylance, Esq., Department of the Navy, for the agency.
Henry J. Gorczycki, Esq., and James A. Spangenberg, Esq., Office of
the General Counsel, GAO, participated in the preparation of the
decision.
DIGEST
Where solicitation states that option prices will be evaluated in
determining which bid offers the lowest overall price for a
construction contract, a bid, which is only low if the option is
considered, is not materially unbalanced where the agency reasonably
expects to exercise the option.
DECISION
MCI Constructors, Inc. protests an award to Danis Heavy Construction
Company under invitation for bids (IFB) No. N62470-94-B-4124, issued
by the Department of the Navy, Naval Facilities Engineering Command,
for the wastewater treatment plant upgrade of the French Creek
Wastewater Treatment Facilities, Marine Corps Base, Camp Lejeune,
North Carolina. MCI contends that Danis's bid should be rejected as
unbalanced.
We deny the protest in part and dismiss it in part.
The existing wastewater treatment facilities at Camp Lejeune do not
comply with National Pollution Discharge Elimination System (NPDES)
Permit No. NC0063029. Camp Lejeune is currently permitted to operate
these facilities under a Special Order of Consent agreement entered
into between Camp Lejeune and the North Carolina Environmental
Management Commission. Under this agreement, compliance with the
NPDES Permit is required by December 31, 1998.
The IFB, issued on May 1, 1996, contemplated award of a firm,
fixed-price construction contract for phases II and III of the
three-phase wastewater treatment plant upgrade project.[1] Phase II
of the project covers the construction of a Sludge Treatment System.
Phase III of the project covers the construction of a Biological
Nutrient Removal (BNR) System. Completion of all three phases of this
project is necessary in order to bring Camp Lejeune's wastewater
treatment facilities into compliance with the NPDES Permit.
The IFB bid schedule contained the following four bid items:
"BID ITEM DESCRIPTION AMOUNT
"0001A Price for entire work (including the total construction
cost for the selected Sludge Treatment System), complete
and in accordance with the drawings & specifications, but
EXCLUDING BID ITEMS 0001B, 0001C AND 0002.
$________
"0001B Price for the present worth of guaranteed total
electrical power consumption for the selected BNR System.
$________
"0001C Price for the present worth of guaranteed total
electrical power consumption for the selected Sludge
Treatment System.
$________
"0002 OPTION ITEM 0001
Price for all work associated with the selected BNR
System (except for associated power consumption covered in
Bid Item 0001B), complete and in accordance with the
drawings and specifications.
$________"
Bid item No. 0002 (phase III of the project) was an option item
because, when the IFB was issued, funds for the military construction
budget had not yet been appropriated. Funds were previously
appropriated for phase I in fiscal year 1994, and for phase II in
fiscal year 1996. Phase III funding was in the fiscal year 1997
military construction budget submitted to Congress.
The IFB required bids on an all-or-none basis for all four bid items.
The base contract would cover only bid item No. 0001A, and the
government reserved the right to exercise the option for bid item No.
0002 within 300 calendar days after contract award.[2] The IFB
incorporated by reference the clause at Federal Acquisition Regulation sec.
52.217-5, Evaluation of Options (July 1990), which states that the
government will include the price of options in its evaluation of
total price for award purposes. The IFB also provided that the low
bid for purposes of award shall be the bid with the lowest total price
for all four bid items.
Bid opening was held on June 11. The Navy received the following
bids:
Bid Item No.
Full decision text continues on ProtestIntel...