Pacific Architects and Engineers, Inc.
Case: B-274405.2
Agency:
Protester: Pacific Architects and Engineers, Inc.
Date: 1996-12-18
Denied
Pacific Architects and Engineers, Inc.
BNUMBER: B-274405.2; B-274405.3
DATE: December 18, 1996
TITLE: Pacific Architects and Engineers, Inc.
**********************************************************************
DOCUMENT FOR PUBLIC RELEASE
A protected decision was issued on the date below and was subject to a
GAO Protective Order. This version has been redacted or approved by
the parties involved for public release.
Matter of:Pacific Architects and Engineers, Inc.
File: B-274405.2; B-274405.3
Date:December 18, 1996
Howell Roger Riggs, Esq., for the protester.
Stuart Young, Esq., and Cheralyn S. Cameron, Esq. for DynCorp, an
intervenor.
Thomas J. Duffy, Esq., Department of the Army, for the agency.
Katherine I. Riback, Esq., Glenn G. Wolcott, Esq., and Paul Lieberman,
Esq., Office of the General Counsel, GAO, participated in the
preparation of the decision.
DIGEST
1. Although agency did not give protester an opportunity to comment
on each individual survey response regarding past performance,
discussions were adequate where agency identified multiple categories
in which protester's past performance was deficient and protester has
not identified any other past performance areas under which its
proposal was downgraded.
2. Agency's cost realism analysis was adequate where the agency
reasonably considered the likely cost of awardee's performance,
including a determination that the awardee's proposed manning levels
were adequate to perform the solicitation tasking requirements.
DECISION
Pacific Architects and Engineers, Inc. (PAE) protests the Department
of the Army's award of a contract to DynCorp under request for
proposals (RFP) No. DAHC92-95-R-0132. PAE, the incumbent contractor,
argues that the agency failed to conduct adequate discussions,
improperly evaluated its proposal, and failed to perform an adequate
cost realism analysis.[1]
We deny the protest.
BACKGROUND
On April 26, 1996, the agency issued the RFP, seeking proposals to
provide base operations support services (BOSS) to the Army at Soto
Cano Air Base, Honduras. The RFP contemplated the award of a
cost-plus-award-fee contract for a base period with four 1-year option
periods.
The solicitation provided that proposals would be evaluated, in
descending order of importance, on the basis of management, technical
and cost factors, and stated that the evaluation would also
incorporate a performance risk assessment.[2] With their proposals,
offerors were required to submit multiple references regarding their
performance of recent contracts for similar services. Under the
management factor, the RFP listed three subfactors, the most important
being past performance. The RFP also provided that award would be
based on the proposal offering the best value to the government
following an integrated assessment of all evaluation factors.
PAE and DynCorp submitted initial proposals by the June 13, 1996,
closing date; each proposal listed multiple past performance
references. Upon receipt, the contracting officer sent past
performance surveys to each reference and subsequently evaluated the
initial proposals. At the time evaluation of initial proposals was
completed, the agency had received past performance responses
regarding two of PAE's prior contracts--the predecessor BOSS contract
at that Soto Cano Air Base and another contract for similar services
performed in Japan.
Following initial evaluation, the agency had certain concerns
regarding PAE's proposal, including negative past performance
information and the agency's conclusion that PAE's proposed manning
levels were excessive. By letters dated June 28, the agency conducted
written discussions with both offerors, which consisted of multiple
"items for negotiation" (IFNs). Discussions with PAE included the
following:
"IFN # 32
Contractor's past performance input from Japan has indicated less
than minimum performance in PAE's internal quality control plan,
contractor's initiative, timely providing adequate resources,
personnel turnover, data reporting and average initiative to
initiate and employ cost savings. Panama's input notes a number
of problems with government property accountability, initiative
to employ cost savings, implementation of TQM and employees
relations training."[3]
Regarding PAE's proposed manning levels, discussions included the
following:
"IFN # 28
Labor Hours. Overall [PAE's proposal] has overestimated the
hours of labor. [PAE's] labor structure more or less resembles
the current contractor labor structure [but] the U.S. labor hours
are higher than current contract hours, and the estimate for
local hours appears to be unreasonabl[y] high. Explain why
[deleted] [hours per year] is used to calculate hours required
under the contract. . .
Full decision text continues on ProtestIntel...